Court rejects Vinci’s claim for €1.6bn over cancelled Nantes airport
12 April 2024
A French court yesterday rejected a claim of nearly €1.6bn in damages made by Vinci in relation to the cancellation of an airport project near Nantes, website BMF Business reports.
The airport was procured as a €580m public-private partnership (PPP), and was to have been completed in 2017.
But the French government cancelled it in 2018 after a long and vehement campaign by environmental activists supported by the Green party.
An administrative court in Nantes found that the government “was not at fault in abandoning the Notre-Dame-des-Landes airport project for reasons of public interest”.
But the court added that, since the project was terminated for reasons of public interest, Vinci should receive “compensation covering the expenses incurred by the concessionaire and its loss of earnings”.
It said this amount would be determined later, and would take into account any gains to Vinci if its concession for the Nantes-Atlantique airport were to be extended.
Related
-
CHINT Highlights Full-Chain Innovation at Intersolar Europe 2025
15 May 2025
-
Bechtel to expand King Salman International Airport in Riyadh
15 May 2025
-
Egis expands energy sector expertise with the acquisition of Omnia Projects
14 May 2025
-
CAF secures $453m maintenance contracts in UK and Colombia
9 May 2025
-
Scatec starts work on $590m solar and battery project
9 May 2025
-
Nordex Group and Consolis inaugurate hybrid tower keystones factory in Riga
9 May 2025