Court rejects Vinci’s claim for €1.6bn over cancelled Nantes airport
12 April 2024A French court yesterday rejected a claim of nearly €1.6bn in damages made by Vinci in relation to the cancellation of an airport project near Nantes, website BMF Business reports.
The airport was procured as a €580m public-private partnership (PPP), and was to have been completed in 2017.
But the French government cancelled it in 2018 after a long and vehement campaign by environmental activists supported by the Green party.
An administrative court in Nantes found that the government “was not at fault in abandoning the Notre-Dame-des-Landes airport project for reasons of public interest”.
But the court added that, since the project was terminated for reasons of public interest, Vinci should receive “compensation covering the expenses incurred by the concessionaire and its loss of earnings”.
It said this amount would be determined later, and would take into account any gains to Vinci if its concession for the Nantes-Atlantique airport were to be extended.
Related
-
Dubai approves designs for $35bn Al Maktoum airport
29 April 2024
-
Iraqi Deputy Prime Minister and Minister of Oil, Hayyan Visits Zhenhua Oil's Ahdeb Oilfield Project
29 April 2024
-
Globeleq acquires the 25 MWp Winnergy solar PV plant in Egypt
29 April 2024
-
Saudi Arabia, China to sign housing project agreements
28 April 2024
-
Rio Tinto, Eramet, LG propose lithium extraction tech for Chile
28 April 2024
-
Anglo American turns down BHP’s $38.8bn buyout bid
28 April 2024