ACWA Power Signs financing agreements for Al Shuaibah 1 and Al Shuaibah 2 PV IPPs
17 July 2023
ACWA Power Co. announces in a statement the finalization and signing of the financing agreements with the financing consortium for Al Shuaibah 1 and Al Shuaibah 2 PV projects at total investment cost of SAR 8.3 billion (USD 2.2 billion), funded by a combination of long-term debt and equity.
The consortium includes ACWA Power; Electricity Holding Company (Badeel), a wholly owned company by the Public Investment Fund (PIF); and Saudi Aramco, with ACWA Power holding a 35% equity stake.
Each Project comprise the development, design, permitting, engineering, financing, procurement, construction, commissioning, testing, completion, ownership, insurance, operation, and maintenance of each Project.
The total financing consists of SAR 6.1 billion (USD 1.6 Billion) senior debt which includes a SAR 1.7 billion (USD 0.45 billion) Saudi Riyal-denominated loan from the National Development Fund (NDF) on behalf of the National Infrastructure Fund (NIF), under foundation. as well as SAR 4.4 billion (USD 1.2 billion) US-dollar denominated commercial facility from a consortium of local, regional and international banks (Bank Saudi Fransi, First Abu Dhabi Bank, Mizuho Bank, Riyad Bank, Saudi National Bank, Standard Chartered Bank and Saudi Investment Bank)
Both Badeel and SNB who are among the parties of this transaction are related parties to ACWA Power in accordance with the regulatory definition of a related party, statement mentioned.
Related
-
Financing signed for largest battery storage system in Romania
24 July 2026
-
Trinasolar and Al-Raebi to explore 1.5GW solar pipeline in Yemen
23 July 2026
-
Chinese contractor appointed for 500MW Oman solar plant
23 July 2026
-
Turkey calls to 2026 renewables auction round
19 July 2026
-
Mitsubishi Power wins contract for Saudi dual-fuel boiler project
15 July 2026
-
Masdar reaches financial close on world-first 24/7 solar project
15 July 2026


京公网安备
11010802030424号
京ICP备19046776号-2