ONE Nuclear Advances 1-GW Iowa Nuclear Project and Explores Transmission Access to PJM
20 November 2026Project Northern Pike targets 1,000 MW of nuclear generation in Cerro Gordo County, with the developer exploring access to a planned 2,100-MW underground transmission link connecting Iowa to Illinois.
ONE Nuclear Energy Inc. is advancing plans for a 1,000-MW nuclear power project in Iowa, with a new transmission development agreement providing a potential route to electricity markets in Illinois and the broader PJM region.
The proposed Project Northern Pike is planned for Cerro Gordo County and is being evaluated as a small modular reactor (SMR) development intended to supply dependable power for growing industrial and computing demand. The project’s development strategy includes exploring transmission access through the proposed SOO Green HVDC Link, a 2,100-MW underground transmission project connecting Iowa and Illinois.
The company is continuing site screening, community engagement and technology evaluation. Final reactor configuration, cooling arrangements, storage capacity and commercial delivery terms have not been established.
ONE Nuclear is targeting first generation in the mid-2030s. The project remains subject to NRC licensing, site development, water availability, interconnection and deliverability studies, power offtake agreements and financing.
SOO Green Link Targets 2,100 MW Transmission Capacity
The proposed SOO Green HVDC Link would connect northern Iowa’s MISO region with the ComEd zone of PJM at Plano, Illinois, creating a potential pathway for electricity to move between the two regional markets.
The underground transmission project would span approximately 350 miles, operate at ±525 kV and carry up to 2,100 MW. SOO Green has updated its target in-service window to Q4 2032 through Q3 2033, citing equipment lead times, supply-chain conditions and outstanding interconnection and offtake arrangements.
ONE Nuclear and SOO Green signed their letter of intent on November 5 to explore potential transmission access for Project Northern Pike. However, the agreement does not reserve transmission capacity or require either party to sign further agreements. Both developments remain independent, and SOO Green plans to operate the line as an open-access facility serving multiple generation resources and electricity buyers.
Iowa’s Nuclear Development Push
Northern Pike comes amid Iowa’s efforts to prepare for potential nuclear investment. The state’s Nuclear Energy Task Force issued nine recommendations in September 2026, including a statewide nuclear feasibility study and a nuclear-ready initiative for host communities.
Iowa also enacted House File 2757, providing sales and use tax exemptions for qualifying nuclear generation facilities, effective July 1, 2026. These measures establish a supportive statewide policy framework, but they do not constitute project-specific approvals or confirm that Northern Pike has secured incentives.
The proposed Iowa development is now moving through site and technology evaluation, with transmission access emerging as a key part of its commercial strategy. However, Northern Pike still needs to secure the approvals, financing, technology and power-delivery arrangements required to advance toward construction.
While nuclear developers explore new sources of firm power to meet growing electricity demand, utility-scale solar continues to expand through major project investments and financing. In Louisiana, Treaty Oak Clean Energy has secured $430 million in tax equity commitments for its 385-MW Beekman and Hollis Creek solar projects, adding to previously secured construction financing as the developments move toward planned commercial operation in 2027.
ONE Nuclear advances its proposed 1,000-MW Iowa nuclear project, exploring transmission access to PJM through the SOO Green link.
Project Northern Pike – Iowa: Factsheet
Developer: ONE Nuclear Energy Inc. (Nasdaq: ONEN) Location: Cerro Gordo County, Iowa Proposed capacity: Up to 1,000 MW (1 GW) Technology: Small modular reactors (SMRs) Project status: Site evaluation and technology development Target first generation: Mid-2030s Battery storage: Capacity undetermined Cooling: Hybrid cooling concept under evaluation Transmission strategy: Potential access to PJM via SOO Green HVDC Link Outstanding requirements: NRC licensing, interconnection, offtake agreements, financing and approvals
SOO Green HVDC Link
Capacity: 2,100 MW Voltage: ±525 kV Length: Approximately 350 miles Route: Northern Iowa to Plano, Illinois Markets: MISO to PJM (ComEd zone) Technology: Underground high-voltage direct current transmission Target in-service window: Q4 2032–Q3 2033 Status: Separate transmission project; no capacity reserved for Northern Pike under the LOI
Iowa Nuclear Policy
Nuclear Energy Task Force final report: September 2026 Task force recommendations: Nine House File 2757: Nuclear tax exemptions and workforce provisions for qualifying developments
Related
-
SOCAR, US-based SLB sign agreement on seismic data processing
20 November 2026
-
PDG and Stockland file to develop Sydney data centers
20 November 2026
-
Hitachi and Bechtel Sign Agreement to Strengthen Delivery of U.S. Power Infrastructure
20 November 2026
-
Shell Pilipinas, Chemrez ink deal for new biodiesel facility in Batangas
20 November 2026
-
Meralco completes 83-MVA transformer upgrade at Commonwealth Substation
20 November 2026
-
M2i signs agreement for critical mineral repository in Nevada
20 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2