Bolivia launches EPC tender for 40 MWac solar project
20 November 2026
Bolivia’s state-owned power utility ENDE has launched an international tender for the engineering, procurement and construction (EPC) of the Contorno Bajo I solar plant, which will have a minimum nominal capacity of 40 MWac. The project will become the first large-scale solar power plant in the department of La Paz.
The tender, published on Nov. 16 under reference ENDE-KFW-2026-002, sets a 14-month implementation period from the signing of the contract. Construction is scheduled to begin in May 2027, with commissioning expected to be completed by June 2028.
The contract includes a 24.9/115 kV step-up substation, an approximately 800-meter-long, 115 kV interconnection line, and modifications to a bay at the Contorno Bajo substation, owned by ENDE Transmisión, to feed electricity into Bolivia’s National Interconnected System (SIN).
Bidders must demonstrate experience in five PV projects of at least 40 MW each and three solar power plants in South America that have been operational for at least two years. They must also demonstrate average annual revenue of at least €60 million ($65.93 million) and access to financial resources totaling €40 million ($43.96 million).
A separate tender for consulting and project supervision services is also underway, with bids due by Dec. 21. The contract covers construction supervision, equipment quality control, plant commissioning and training for ENDE personnel.
In June, the Bolivian government enacted legislation approving a loan of up to €34 million ($37.36 million) from German development bank KfW to finance the project.
According to information released by ENDE in July, the solar plant will occupy 34 hectares at an altitude of more than 3,700 meters above sea level and will have an estimated operational lifetime of 25 years.
The original project design, announced in January 2023, included a lithium-ion battery energy storage system. However, the current tender notice makes no mention of a storage component.
Related
-
Tesla seeks Texas tax break for $3.1 billion polysilicon plant
20 November 2026
-
France’s first canal-top PV project goes online
20 November 2026
-
ChronoScale and STN form JV to develop data center campus in Odessa, Texas
20 November 2026
-
LONGi to supply solar modules for Muswellbrook Solar Farm project in Australia
20 November 2026
-
Mitsubishi Heavy Industries and Sakura Internet sign MoU to establish sovereign AI infrastructure in Japan
20 November 2026
-
PDG secures additional $210m for its TY1 Tokyo Campus
20 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2