$297 mln gas-fired power project in central Vietnam seeks new investor

20 November 2026

Following the withdrawal of Russia's Gazprom Group from the Quang Tri combined-cycle gas turbine (CCGT) power plant project, authorities in Quang Tri province have added the project to their list of investment priorities for 2026-2030.

A gas-fired power plant developed by Russia's Gazprom Group. Photo courtesy of Sigmalive.

A gas-fired power plant developed by Russia's Gazprom Group.

Under a decision by the provincial People's Committee approving a list of 103 projects prioritized for investment during the period, the project will cover 42.23 hectares in My Thuy commune, within the Southeast Quang Tri Economic Zone.

It involves the construction of a 340 MW combined-cycle gas turbine power plant, with capacity potentially increased to match the reserves of the Bao Vang gas field.

According to the committee, the project is consistent with the approved master plan for the Southeast Quang Tri Economic Zone. The site will be connected to the extended National Highway 15D, which links to the economic zone.

In March 2020, the government approved the assignment of Gazprom EP International B.V. (Gazprom International), a subsidiary of Russia's Gazprom Group, to develop the Quang Tri combined-cycle gas turbine power plant under a build-operate-transfer (BOT) contract.

Under the design, the plant would have a capacity of 340 MW and use combined-cycle gas turbine technology. Total investment was estimated at $297 million, with construction expected to take about 27 months. Its primary fuel sources would be natural gas extracted from offshore fields in Quang Tri and imported gas.

The project was designed to use natural gas from the Bao Vang field and was initially expected to begin operations in 2023-2024. It was subsequently carried over into the Power Development Plan VIII (PDP VIII) and its revised version, with an operational timeline of 2026-2030.

Upon completion, the project is expected to play an important role in developing Quang Tri's industrial and service sectors, while supporting infrastructure development, including ports and transport networks, in the Southeast Quang Tri Economic Zone.

However, more than five years after being assigned as the investor, Gazprom International had yet to undertake the procedures required under current laws governing public-private partnership (PPP) investment, despite repeated follow-ups by the provincial authorities.

According to the Quang Tri Department of Industry and Trade, on March 6, 2026, Gazprom International issued a document in response to inquiries about the project's implementation.

The firm said Gazprom Group, its parent company, had decided that continuing exploration of the Bao Vang field and proceeding with development of the integrated project were not appropriate at this time.

As a result, Gazprom International was forced to decline participation in the construction of the combined-cycle gas turbine power plant in Quang Tri. It also provided information on another partner that had expressed interest in taking the project forward.

Specifically, Petrovietnam Exploration Production Corporation (PVEP), a partner of Gazprom International, expressed its intention to proactively continue implementing petroleum contracts in Blocks 112, 113 and 111/04 on Vietnam's continental shelf, including further exploration of the Bao Vang field.

PVEP also expressed interest in the proposed combined-cycle gas turbine power plant project in Quang Tri.

The provincial People's Committee has asked the Ministry of Industry and Trade to provide guidance on procedures for terminating Gazprom International's investor status and restructuring the project to ensure its implementation schedule remains aligned with the revised PDP VIII.

The Bao Vang gas field is located offshore in the Song Hong basin, approximately 100 kilometers from the Quang Tri coastline. According to Gazprom's exploration results, the combined gas reserves of the Bao Vang and neighboring Bao Den fields total 57.88 billion cubic meters. Of this, the proven reserves directly identified in Blocks 111-113, where the Bao Vang field is located, amount to approximately 1.5 billion cubic meters.

In addition to Bao Vang, Quang Tri is also home to the Ken Bau gas field, located about 65 kilometers offshore. The large oil and gas field lies in Block 114, offshore on Vietnam's northern continental shelf in the Song Hong basin.

Previously, Eni Vietnam, part of Italy's Eni Group, conducted surveys and exploration at the field, identifying estimated in-place resources of 7-9 trillion cubic feet (Tcf) of natural gas and 400-500 million barrels of oil.

Under PDP VIII, Ken Bau was initially reported to have substantial reserves, potentially sufficient to support gas-fired power generation capacity of around 4,000-6,000 MW. However, two appraisal drilling attempts were unsuccessful, and the field is now expected to be developed during 2031-2035.