First 2,000 MW Gas-to-Power Tender in South Africa Fails Over Fuel Supply Risks
28 October 2026
The first gas-to-power tender in South Africa has failed to appoint preferred bidders after developers were unable to provide the required assurances of natural gas supply, dealing a setback to the country’s plans to diversify its electricity generation mix.
South Africa’s Department of Electricity and Energy confirmed on October 28, 2026, that none of the four bids submitted under the first bidding window of the Gas Independent Power Producer Procurement Program (GASIPPPP) met the mandatory requirements for gas supply. The tender had targeted 2,000 MW of new electricity generation capacity.
The Independent Power Producers (IPP) Office received the four bids on May 29, 2026. They offered a combined 2,830 MW of proposed generation capacity. Despite the total capacity exceeding the government’s procurement target, the proposals failed to satisfy the tender’s fuel-supply requirements.
South Africa’s inaugural tender fail highlights a major challenge facing the country’s emerging gas-to-power sector. The country still grapples to secure dependable and commercially viable fuel supplies before new power stations can be developed and operated.
According to the department of energy, the government will continue pursuing its gas-to-power objectives. This is while engaging with market participants to address the infrastructure, commercial and institutional barriers affecting project delivery. The timing and requirements of any subsequent procurement round remain subject to further consultation and the necessary approvals.
South Africa’s gas supply constraints threaten new power projects
South Africa’s gas-to-power ambitions face growing uncertainty as existing supplies from neighboring Mozambique decline. The country imports most of its natural gas from Mozambique. Declining production from established fields in Mozambique threaten supplies to South African industrial users in the coming years.
This creates a significant challenge for developers seeking to establish new gas-fired power plants. Even where projects attract investment interest and offer sufficient generating capacity, the absence of secure long-term fuel supply arrangements can prevent them from progressing through procurement and financing.
To address the supply gap, South Africa is developing its first liquefied natural gas (LNG) import terminal, with ExxonMobil and state-owned power utility Eskom identified as anchor clients. The development of LNG import infrastructure could provide access to international gas markets and support the expansion of gas-fired electricity generation.
However, the failed gas-to-power tender in South Africa shows just how important the coordination between power generation investments and other factors such as fuel procurement and import infrastructure is. Other factors include transportation networks and long-term supply contracts.
South Africa’s Gas Independent Power Producer Procurement Program (GASIPPPP), Bid Window 1: Key Facts
Related
-
UK government approves nearly 2 GW of co-located solar in October
29 October 2026
-
Uzbekneftegaz, Petronas discuss long-term gas supplies, joint projects
28 October 2026
-
Webuild selected as preferred bidder for Lot 1B of Zambia Lobito Railway Corridor supported by Italy’s Mattei Plan
28 October 2026
-
Baltica 2 Offshore Wind Project: BGB Group Joins $4.5bn Development for Substation Construction
28 October 2026
-
Samsung SDI signs 1GWh US BESS supply agreement with Alpha Omega Power
28 October 2026
-
Giga Storage closes €260 million debt financing for 1,400MWh Germany BESS
28 October 2026


京公网安备
11010802030424号
京ICP备19046776号-2