Spain launches call for access to 3.68 GW of grid capacity
19 July 2025
Spain's Ministry for Ecological Transition and the Demographic Challenge (MITECO) has launched its first tender to allocate grid capacity at eight electricity transmission nodes in Andalusia, Aragon, Castilla-La Mancha, Catalonia, Galicia, and the Basque Country.
The total access capacity amounts to 3,681 MW and corresponds to nodes where major industrial developments have submitted requests.
These grid points are oversubscribed with applications from large consumers. Until now, each request was evaluated individually. Due to overloads at some nodes, a competitive process has been introduced. When grid operator Red Eléctrica de España (REE) receives a demand access request for a specific node, it publishes it on its website.
If additional requests are submitted within one month and available capacity is insufficient, the node is assigned to a tender among all interested parties who expressed interest during that period.
Applicants have one month to submit the required documentation. After review, which may include a report from REE, MITECO will resolve each tender within six months of the call. Developers must submit financial guarantees based on three criteria, amounting to €25/kW for each criterion. These guarantees will be returned once compliance is verified.
This is the first time demand access is allocated through a regulated tender using three evaluation criteria. The process marks a shift, giving preference to projects that reduce CO₂ emissions, such as electrifying industrial processes. After this initial criterion, projects will be scored based on investment size and expected commissioning timelines. The criteria include:
Emissions reduction (decarbonization impact)
Planned investment volume
Timeline for consumption start-up
The eligible nodes and available capacity are:
Arrigorriaga (Bizkaia) 400 kV – 993 MW
Brazatortas (Ciudad Real) 400 kV – 1,217 MW
Cristóbal Colón (Huelva) 220 kV – 503 MW
Francolí (Tarragona) 220 kV – 216 MW
Mercedes Benz (Vitoria) 220 kV – 387 MW
New Vigo 220 kV – 182 MW
Palos (Huelva) 220 kV – 277 MW
Terrer (Zaragoza) 400 kV – 410 MW
Related
-
Sumitomo Acquires 49% of Hero Group's 500 MWp Solar-Wind Project with Storage
13 October 2026
-
Alstom, Vingroup to supply up to 200 metro trains for Hanoi
13 October 2026
-
Discovery to acquire McEwen’s Timmins mineral assets for $55m
13 October 2026
-
Boskalis wins contract to install 149 km of inter-array cables at the Zeevonk offshore wind farm in the Netherlands
13 October 2026
-
Eskom kicks off tender for 6 GW of renewables-plus-storage
13 October 2026
-
Thiess secures two-year mining services contract extension at Okvau Gold Project, Cambodia
13 October 2026


京公网安备
11010802030424号
京ICP备19046776号-2