Spain launches call for access to 3.68 GW of grid capacity
19 July 2025
Spain's Ministry for Ecological Transition and the Demographic Challenge (MITECO) has launched its first tender to allocate grid capacity at eight electricity transmission nodes in Andalusia, Aragon, Castilla-La Mancha, Catalonia, Galicia, and the Basque Country.
The total access capacity amounts to 3,681 MW and corresponds to nodes where major industrial developments have submitted requests.
These grid points are oversubscribed with applications from large consumers. Until now, each request was evaluated individually. Due to overloads at some nodes, a competitive process has been introduced. When grid operator Red Eléctrica de España (REE) receives a demand access request for a specific node, it publishes it on its website.
If additional requests are submitted within one month and available capacity is insufficient, the node is assigned to a tender among all interested parties who expressed interest during that period.
Applicants have one month to submit the required documentation. After review, which may include a report from REE, MITECO will resolve each tender within six months of the call. Developers must submit financial guarantees based on three criteria, amounting to €25/kW for each criterion. These guarantees will be returned once compliance is verified.
This is the first time demand access is allocated through a regulated tender using three evaluation criteria. The process marks a shift, giving preference to projects that reduce CO₂ emissions, such as electrifying industrial processes. After this initial criterion, projects will be scored based on investment size and expected commissioning timelines. The criteria include:
Emissions reduction (decarbonization impact)
Planned investment volume
Timeline for consumption start-up
The eligible nodes and available capacity are:
Arrigorriaga (Bizkaia) 400 kV – 993 MW
Brazatortas (Ciudad Real) 400 kV – 1,217 MW
Cristóbal Colón (Huelva) 220 kV – 503 MW
Francolí (Tarragona) 220 kV – 216 MW
Mercedes Benz (Vitoria) 220 kV – 387 MW
New Vigo 220 kV – 182 MW
Palos (Huelva) 220 kV – 277 MW
Terrer (Zaragoza) 400 kV – 410 MW
Related
-
Korean bank backs Guam’s largest solar project
28 December 2025
-
Masdar completes first project in £1 Billion UK BESS investment and announces project pipeline
26 December 2025
-
Masdar signs PPA for 200 MW floating solar project in Malaysia
25 December 2025
-
Mubadala teams up with Actis to invest in Rezolv Energy
25 December 2025
-
Saeta Yield closed €340 million refinancing and secures €200 million RCF in Europe
25 December 2025
-
TotalEnergies sells half of 424 MW portfolio in Greece
24 December 2025


京公网安备
11010802030424号
京ICP备19046776号-2