Montenegro sets ceiling price of €65/MWh for first solar auction
11 July 2025
The government of Montenegro has set the conditions for the country’s first solar auction.
The auction will accept bids for solar projects with a minimum capacity of 400 kW, offering up to 250 MW of total capacity. It is the first in a planned series of market premium auctions targeting 400 MW of new solar and wind capacity.
The government has set a ceiling price of €65/MWh for the auction. Winners will be those that propose the lowest strike price and will be awarded a 12-year contract for difference.
The auction also features a clause that allows its quota to be extended by up to 20%, or 50 MW, to facilitate bids that are similarly ranked. It is anticipated the auction will open by the third quarter of this year.
Montenegro’s cumulative solar capacity reached 30 MW by the end of 2024, up from 17 MW at the end of the year prior, according to figures from the International Renewable Energy Agency (IRENA).
The country has set a target of a 50% renewable energy share in final consumption and a 70% renewable energy share in electricity production by the end of the decade.
Related
-
Iraq risks defaulting on payments for $10bn oil project
21 May 2026
-
Masdar and EPCG to form joint venture to develop renewable energy projects in Montenegro
27 April 2026
-
Danantara forms Denera to expand waste-to-energy push
10 April 2026
-
IFC loans $125 million for polysilicon factory in Malaysia
31 March 2026
-
Iraq hit by nationwide electricity blackouts
6 March 2026
-
Greece to open applications for 130 MW agrivoltaics plan
5 March 2026


京公网安备
11010802030424号
京ICP备19046776号-2