The Construction of Cambodia Upper Tatay Hydropower Station Reached a Milestone
21 June 2024On May 31, 2024, the filling of the Kep River Dam of the Upper Tatay Hydropower Station in Cambodia reached the flood height of 353 meters as scheduled, marking the successful completion of the most important milestone of the Project in 2024.
Since the dam filling project started on March 1, 2023, the project management team has been united and brave, actively coordinating the construction units, and fully promoting the construction process, at the same time, lean management, overcome difficulties, strictly observe the safety and quality of the project, and escort the project construction.
The Kep River dam is a concrete face and rock-fill dam with a crest elevation of 375 meters, a maximum dam height of 69 meters, and a dam axis length of 1120 meters. At present, the dam filling has reached the flood height of 353 meters, which has laid a solid foundation for the subsequent construction.

Related
-
UAE’s Masdar starts operations at 35MW/70MWh UK battery storage project
28 August 2026
-
Samsung E&A repairs Kuwait refinery after attacks
27 August 2026
-
ACCIONA Energía to install two new battery energy storage systems in Spain
25 August 2026
-
PowerChina wins 30 MW solar project in North Macedonia
24 August 2026
-
PowerChina wins $1.32bn deal for Iraq water project
19 August 2026
-
Bahrain opens prices for transaction advisory services on Northern Link Road
11 August 2026


京公网安备
11010802030424号
京ICP备19046776号-2