The Construction of Cambodia Upper Tatay Hydropower Station Reached a Milestone
21 June 2024On May 31, 2024, the filling of the Kep River Dam of the Upper Tatay Hydropower Station in Cambodia reached the flood height of 353 meters as scheduled, marking the successful completion of the most important milestone of the Project in 2024.
Since the dam filling project started on March 1, 2023, the project management team has been united and brave, actively coordinating the construction units, and fully promoting the construction process, at the same time, lean management, overcome difficulties, strictly observe the safety and quality of the project, and escort the project construction.
The Kep River dam is a concrete face and rock-fill dam with a crest elevation of 375 meters, a maximum dam height of 69 meters, and a dam axis length of 1120 meters. At present, the dam filling has reached the flood height of 353 meters, which has laid a solid foundation for the subsequent construction.
Related
-
CEEC JTC 118 MW solar project in Singapore connected to grid
10 January 2025
-
Skanska invests CZK 956M, about SEK 440M, in a new phase of a residential project in Prague, Czech Republic
10 January 2025
-
Renalfa IPP buys 258 MW solar project in Romania, plans to install 1 GWh BESS
10 January 2025
-
Norway plans SMR plant to power future data centres
9 January 2025
-
Croatia plans solar tenders in 2025
9 January 2025
-
Romania finances 1.5 GW solar panel factory
9 January 2025