Critical Milestones for the Substation and the PV Plant of 20MW Gifu Solar Power Plant Project Completed
5 June 2024Recently, the 20MW Gifu Solar Power Plant Project in Japan, EPC contracted by China Energy Engineering Group Shanxi Electric Power Engineering Co., Ltd. (SEPEC), has successfully completed two important milestones: the overall withstand voltage test of the substation and the installation of all PV Modules. The project is now in a new phase of construction.

On May 10, the overall withstand voltage test of the substation passed at once. This success marks the basic completion of the electrical debugging of the substation, laying a solid foundation for achieving the project's grid connection goals.
On May 25, all PV Modules were installed despite various difficulties such as complex site conditions, extensive construction scope, frequent earthquakes, and winter conditions.
The 20MW Gifu Solar Power Plant Project is the first new energy project EPC constructed by China Energy Engineering Group Shanxi Electric Power Engineering Co., Ltd. (SEPEC) in Japan. The project is located in Takayama City, Gifu Prefecture, central Japan. The project covers a total area of 117 hectares, divided into 16 plots for construction, and is accompanied by the construction of a 154kV substation.

Next, the PV plant of the project will enter a critical phase involving cable laying, wiring, and equipment debugging. The entire project team will continue to exert their efforts, striving with full force towards achieving the goal of full-capacity grid connection and operation.
Related
-
Sabey Data Centers signs 10-year Texas solar agreement covering 43.5 MW
19 November 2026
-
Updated cost estimate for the Snøhvit Future project
18 November 2026
-
CO₂ research project “catch4climate” officially inaugurated with 200 guests from politics and industry
18 November 2026
-
LA ABC, GOBERNACIÓN Y TRANSPORTE ACUERDAN REINICIAR TRABAJOS DE SELLADO DE JUNTAS, BERMAS Y MANTENIMIENTO CONSTANTE EN EL DESVÍO PARA REACTIVAR LA DOBLE VÍA ORURO – CHALLAPATA
18 November 2026
-
Webuild: first span being raised for Vallone delle Coste Viaduct on Ragusa-Catania Highway
18 November 2026
-
OMV receives EUR 450 mn loan from the European Investment Bank for its 140 MW green hydrogen production facility
17 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2