Cameroon's Nachtigal Hydro Project 93% Complete
7 May 2024
Construction of the 420MW Nachtigal hydropower project on the Sanaga River in Cameroon has crossed 93% completion, and the first turbine is due to be commissioned this month.
The independent power project is being developed by Nachtigal Hydro Power Company (NHPC) under a 35-year concession.
NHPC is a special purpose vehicle comprising France’s EDF (40%), the IFC (20%), the Cameroon government (15%), Africa50 (15%) and impact fund STOA (10%).
The €1.2 billion (US$1.3 billion) project entails the construction of a 1.5km-long and 14-metre-high dam, with a 3.3km headrace channel, and a power plant housing seven 60MW turbines.
Belgium’s BESIX, France’s NGE Contracting and Morocco’s SGTM are executing the main civil works, while Spain’s Elecnor is undertaking the electro-mechanical works in consortium with the US’ GE Renewable Energy.
As of the end of March, the civil works had reached 94.5% completion, while the electro-mechanical works were 89.4% finished. The full commissioning of the plant is due by the end of this year.
Once fully operational, the Nachtigal facility will be able to meet 30% of Cameroon’s power needs. Installation of the 50km-long 225kv transmission lines connecting the plant to the grid were completed by France's Bouygues Energy & Services in September 2021. The transformer substation was energised at the end of February.
Related
-
Korean bank backs Guam’s largest solar project
28 December 2025
-
Masdar completes first project in £1 Billion UK BESS investment and announces project pipeline
26 December 2025
-
Masdar signs PPA for 200 MW floating solar project in Malaysia
25 December 2025
-
Mubadala teams up with Actis to invest in Rezolv Energy
25 December 2025
-
Saeta Yield closed €340 million refinancing and secures €200 million RCF in Europe
25 December 2025
-
TotalEnergies sells half of 424 MW portfolio in Greece
24 December 2025


京公网安备
11010802030424号
京ICP备19046776号-2