Cameroon's Nachtigal Hydro Project 93% Complete
7 May 2024
Construction of the 420MW Nachtigal hydropower project on the Sanaga River in Cameroon has crossed 93% completion, and the first turbine is due to be commissioned this month.
The independent power project is being developed by Nachtigal Hydro Power Company (NHPC) under a 35-year concession.
NHPC is a special purpose vehicle comprising France’s EDF (40%), the IFC (20%), the Cameroon government (15%), Africa50 (15%) and impact fund STOA (10%).
The €1.2 billion (US$1.3 billion) project entails the construction of a 1.5km-long and 14-metre-high dam, with a 3.3km headrace channel, and a power plant housing seven 60MW turbines.
Belgium’s BESIX, France’s NGE Contracting and Morocco’s SGTM are executing the main civil works, while Spain’s Elecnor is undertaking the electro-mechanical works in consortium with the US’ GE Renewable Energy.
As of the end of March, the civil works had reached 94.5% completion, while the electro-mechanical works were 89.4% finished. The full commissioning of the plant is due by the end of this year.
Once fully operational, the Nachtigal facility will be able to meet 30% of Cameroon’s power needs. Installation of the 50km-long 225kv transmission lines connecting the plant to the grid were completed by France's Bouygues Energy & Services in September 2021. The transformer substation was energised at the end of February.
Related
-
Eni to invest $8bn in Egypt’s energy sector
1 October 2025
-
China’s Asia-Potash plans $1.6bln fertiliser complex in Algeria
30 September 2025
-
Qatar’s UCC Holding announces the launch of Damascus International Airport Project
29 September 2025
-
Wabtec secures $4.2bn locomotive order from Kazakhstan
29 September 2025
-
Mexico launches tender for 300 MW solar plant
28 September 2025
-
Namibia approves 3 GW of solar for hydrogen production
28 September 2025