Cameroon's Nachtigal Hydro Project 93% Complete
7 May 2024
Construction of the 420MW Nachtigal hydropower project on the Sanaga River in Cameroon has crossed 93% completion, and the first turbine is due to be commissioned this month.
The independent power project is being developed by Nachtigal Hydro Power Company (NHPC) under a 35-year concession.
NHPC is a special purpose vehicle comprising France’s EDF (40%), the IFC (20%), the Cameroon government (15%), Africa50 (15%) and impact fund STOA (10%).
The €1.2 billion (US$1.3 billion) project entails the construction of a 1.5km-long and 14-metre-high dam, with a 3.3km headrace channel, and a power plant housing seven 60MW turbines.
Belgium’s BESIX, France’s NGE Contracting and Morocco’s SGTM are executing the main civil works, while Spain’s Elecnor is undertaking the electro-mechanical works in consortium with the US’ GE Renewable Energy.
As of the end of March, the civil works had reached 94.5% completion, while the electro-mechanical works were 89.4% finished. The full commissioning of the plant is due by the end of this year.
Once fully operational, the Nachtigal facility will be able to meet 30% of Cameroon’s power needs. Installation of the 50km-long 225kv transmission lines connecting the plant to the grid were completed by France's Bouygues Energy & Services in September 2021. The transformer substation was energised at the end of February.
Related
-
ANDRITZ wins major hydropower upgrade contract in New Zealand
22 April 2026
-
Romania's Bihor county signs EU funding deal for 281 mln euro tram-train project
22 April 2026
-
SANY Group to build giant hybrid power complex in Romania with data center
21 April 2026
-
Wärtsilä to supply 412MW of engine power for US data centre
20 April 2026
-
Samsung C&T, Hitachi Energy partner on European power grid market entry
19 April 2026
-
HiTHIUM to invest in the gigafactory of BESS and cell in Spain
19 April 2026


京公网安备
11010802030424号
京ICP备19046776号-2