North Macedonia to ink first agreement with strategic investor for solar park
8 February 2024
North Macedonia has prepared the first law and agreement on a strategic investment in renewable energy for the 70 MW Pehčevo solar power plant project. The model is used to facilitate and speed up investments in renewable energy projects.
In 2020, Macedonia passed the Law on Strategic Investments to encourage, attract and create conditions for the implementation of strategic investments. Under the procedure, the government first decides to grant the status to a project. So far there are 12 on the list, of which the vast majority is for renewables. They include Green Energy Factory, Mytilineos’ proposed cogeneration facility in Skopje, Stipion, Erdželija, Pehčevo and Virovi.
Next, the government negotiates with the investor, aiming to produce a law and an agreement, which the parliament must adopt.
The government has adopted the bill for the solar power plant in Pehčevo and sent it to lawmakers. An integral part of the proposal is the strategic investment project agreement between the government and HEC Solar MK, the investor.
The investor plans to invest almost EUR 52 million. The firm would secure financing from commercial and development banks, international financial institutions and international funds, the bill reads.
According to the document, the investor can install agrisolar systems. The project is located on state land, which the investor would lease.
Every six months since the start of the commercial operation of the photovoltaic plant, and until its decommissioning, the investor is obligated to pay, to the Development Fund organized by the Development Bank of North Macedonia, EUR 1 per MWh of all electricity that it sells.
The investor will issue a EUR 1.56 million bank guarantee in favour of the government, the bill adds.
According to the document, its adoption doesn’t require funds from the budget.
The agreement between the government and the investor would be valid for 25 years. The firm will sign a power purchase agreement (PPA) with state-owned power utility Elektrani na Severna Makedonija (ESM), the deal stipulates.
The investor has 26 months to complete the project design and obtain permits, and another 24 months to build the solar park, according to the agreement.
Related
-
US agency to do more equity investing in Africa, official says
10 October 2026
-
GEN İlaç (Türkiye) Inaugurates Pharmaceutical Plant in Azerbaijan
9 October 2026
-
2 GW TOYO Solar Module Factory: Expansion Completed in Humble, Texas
9 October 2026
-
Oracle, Broadcom, and SpaceX looking to secure ten of billions in financing to support AI compute purchases – report
9 October 2026
-
Sumitomo to invest in 500MWp renewable energy project in India
9 October 2026
-
Chevron signs Egypt oil and gas exploration deal
8 October 2026


京公网安备
11010802030424号
京ICP备19046776号-2