Skanska builds power projects in Vestland County, Norway, for NOK 1.9 billion, about SEK 1.9 billion
24 January 2024
Skanska has signed a contract with Aker BP for the construction of a transformer station and a compensation station in Vestland County, Norway. The contract is worth NOK 1.9 billion, about SEK 1.9 billion, which will be included in the Nordic order bookings for the first quarter 2024.
The contract consists of both building and construction work related to a new transformer station in Børdalen in Samnanger municipality, as well as a compensation station at Årskog in Fitjar municipality.
The construction works is ongoing, and the project is expected to be completed during the autumn 2025.
Related
-
Sabey Data Centers signs 10-year Texas solar agreement covering 43.5 MW
19 November 2026
-
Agreement on concept for Ringvei Vest – combining several discoveries in one project
18 November 2026
-
Equinor’s Capital Markets Day 2026
18 November 2026
-
Expanding Troll: more gas to Europe
18 November 2026
-
Oil and gas discovery in the North Sea adding volumes to Oseberg
18 November 2026
-
Collaborating to develop challenging discoveries
18 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2