26 September 2023
Electricity and Water Authority (EWA), Bahrain received bidder’s Proposal for the Transformer and Reactor Works for new 400kV Jasra Grid Substation.
The following three bidders submitted the proposals.
- Hitachi Energy – BHD 18,720,966.690
- FUJI ELECTRIC – BHD 19,960,338.056
- HD Hyundai Electric – BHD 20,696,363.505
As per tender notification, EWA proposes to launch a project for establishment of a new 400kV Jasra Grid Substation. The Transformer and Reactor Works is one of the Project work packages intended to be executed through international limited tender.
The scope of this tender includes the Design, manufacturing, supply, transportation, erection, testing and commissioning of 4 nos. 400 220 21kV, 500MVA Autotransformer, 3 nos. 400kV, 100MVAr feeder reactors, and 4 nos. 21kV, 25MVAr transformer tertiary reactors. It includes also Design, manufacturing, supply, transportation, erection, testing and commissioning of Water Deluge System for fire protection of transformers, reactors, DG and Fuel Tank.
Related
-
On behalf of His Majesty King Abdullah II, His Royal Highness Prince Faisal bin Al Hussein lays the Foundation Stone for the National Water Conveyance Project, with Arab Contractors’ Participation
19 November 2026
-
Sabey Data Centers signs 10-year Texas solar agreement covering 43.5 MW
19 November 2026
-
$900bn Anthropic Data Centre Construction Bet Shapes AI Infrastructure Expansion
19 November 2026
-
$785M Los Alamos Computing Facility advances towards construction approval in University of Michigan
19 November 2026
-
Intermountain Health Breaks Ground on New 521,000-Square-Foot LDS Hospital in Salt Lake City
19 November 2026
-
Northern Vietnam's Hai Phong leases 103.6 hectares for Singapore-backed $945 mln port project
18 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2