Skanska awarded an additional GBP 103M, about SEK 1.3 billion, towards works on the high-speed railway HS2 in UK
3 July 2023
Skanska, as part of the Skanska Costain STRABAG joint venture, has been awarded an additional GBP 103M, about SEK 1.3 billion, under the existing contract with HS2 Ltd towards works on phase one of the new high-speed railway in the UK. This will be included in the order bookings for Europe in the second quarter of 2023.
The award relates to planned and agreed changes to the scope of works under the contract.
The total contract, now valued at approximately GBP 1.3 billion, about SEK 16.6 billion to Skanska, involves the design and construction of major tunnels in the southern section of the overall project.
Since being given notice to proceed by HS2 Ltd in April 2020, significant progress has been made. Two tunnel boring machines (TBMs) started operations in late 2022 from West Ruislip Portal towards Green Park Way. They will construct 8 kilometers (5 miles) of the 13.5-kilometer (8.4 mile) twin bored Northolt Tunnel. Two further TBMs have been received in the UK and will be launched in the next year from Victoria Road Crossover Box. A third TBM is currently in operation from Atlas Road, constructing a logistics tunnel between Old Oak Common station site and the Atlas Road site. The preparation works for the launch of the two final TBMs from the Old Oak Common Box towards Euston will begin in 2024.
Related
-
Saudi contractor awarded $121m housing construction contracts
17 September 2025
-
QatarEnergy signs 2GW Dukhan solar plant deal with Samsung
17 September 2025
-
EDP completes deal for 121 MW wind portfolio in France and Belgium
16 September 2025
-
Miahona pens deals for water infrastructure projects in Uzbekistan
12 September 2025
-
Hyundai Rotem keen on developing high-speed railways in Vietnam
12 September 2025
-
Hanoi approved plan to build the fifth metro line
12 September 2025