Nesma awarded SAR68m 115kV Transmission Line Project
5 May 2023
Nesma Infrastructure & Technology (NIT), Saudi Arabia announced in a statement that it has been awarded a contract by National Grid to construct a 115kV overhead transmission line between Ain Dar and Abqaiq, more than 40 kilometers.
The SAR 68 million project will be completed in three phases and will include the construction of 125 towers.
The project is expected to take 25 months to complete.
The construction of the transmission line is an important project that will provide a reliable connection between Ain Dar and Abqaiq, improving the overall efficiency of the electricity transmission network in the region and providing a reliable supply to customers, statement mentioned.
Related
-
Sungrow to supply PV inverter solutions for San Martín project in Peru
24 November 2025
-
Novi Sad plans to build waste-to-energy cogeneration plant
24 November 2025
-
ADB approves $330m loans for clean energy transmission in Pakistan
22 November 2025
-
Google plans €5.5bn infrastructure investment in Germany
22 November 2025
-
Hyundai begins work on hydrogen fuel cell plant in Korea
21 November 2025
-
France’s first simplified solar tender draws limited developer interest
20 November 2025


京公网安备
11010802030424号
京ICP备19046776号-2