Bahrain received Bids for 400kV Jasra Grid Substation
7 February 2023
Electricity and Water Authority (EWA), Bahrain received Bidders Proposals for the Substation Switchgear, Systems & Civil Works of new 400kV Jasra Grid Substation.
Following Bidders has submitted the proposals:
- Grid Solutions – Option 1: BHD 54,546,371.219; Option 2: 64,783,282.519
- Linxon – BHD 71,304,100.736
- Siemens – Option 1: BHD 64,664,884.514; Option 2: 49,636,505.389
As per the tender notification, EWA proposes to launch a project for establishment of a new 400kV Jasra Grid Substation.
The Substation Switchgear & Civil Works is one of the Project work packages intended to be executed through international limited tender.
The scope of this tender includes Design, manufacturing, supply, transportation, erection, testing and commissioning of 400kV Grid substation at Jasra includes 400kV GIS, 220kV GIS, 21kV switchgear, Control, Protection and ICS, Telecom systems and associated substation cabling etc. also includes Civil works of the substation and associated building services including CCTV and Electronic Access Control systems.
The tender excludes the 400kV Power Transformer and Reactor Works as well as 400kV and 220kV feeder Cable works, which are under other work packages.
Earlier, EWA received the bidders proposals for 400kV Underground cable works and Transformer and Reactor Works.
Related
-
Developers appoint contractor for $500m wastewater treatment project
16 February 2026
-
Alstom and Terna team win €992m Romania rail contract
14 February 2026
-
VinSpeed teams up with Siemens Mobility for Vietnam high-speed rail project
12 February 2026
-
Axpo, Enhol sign ten-year PPA for 3.7TWh in Spain
12 February 2026
-
Riyadh qualifies six groups for One-Stop Stations PPP
3 February 2026
-
Contractors submit Riyadh Metro Line 7 bids
3 February 2026


京公网安备
11010802030424号
京ICP备19046776号-2