Bahrain received Bids for 400kV Jasra Grid Substation
7 February 2023Electricity and Water Authority (EWA), Bahrain received Bidders Proposals for the Substation Switchgear, Systems & Civil Works of new 400kV Jasra Grid Substation.
Following Bidders has submitted the proposals:
- Grid Solutions – Option 1: BHD 54,546,371.219; Option 2: 64,783,282.519
- Linxon – BHD 71,304,100.736
- Siemens – Option 1: BHD 64,664,884.514; Option 2: 49,636,505.389
As per the tender notification, EWA proposes to launch a project for establishment of a new 400kV Jasra Grid Substation.
The Substation Switchgear & Civil Works is one of the Project work packages intended to be executed through international limited tender.
The scope of this tender includes Design, manufacturing, supply, transportation, erection, testing and commissioning of 400kV Grid substation at Jasra includes 400kV GIS, 220kV GIS, 21kV switchgear, Control, Protection and ICS, Telecom systems and associated substation cabling etc. also includes Civil works of the substation and associated building services including CCTV and Electronic Access Control systems.
The tender excludes the 400kV Power Transformer and Reactor Works as well as 400kV and 220kV feeder Cable works, which are under other work packages.
Earlier, EWA received the bidders proposals for 400kV Underground cable works and Transformer and Reactor Works.
Related
-
Bhutan awards 120 MW solar contract
8 August 2025
-
Bahrain goes to market with first solar IPP project
7 August 2025
-
Bilfinger wins feed contract for Kuwait refinery pier
7 August 2025
-
Firms submit Al-Maktoum airport rail system bids
7 August 2025
-
Uzbekistan certifies first solar plant under I-REC system
6 August 2025
-
AMEA Power joins €250 million Agadir desalination project in Morocco
5 August 2025