Singapore starts work on first phase of $30bn Cross Island Line
30 January 2023
Singapore’s Land Transport Authority (LTA) has announced the beginning of work on phase one of the Cross Island Line (CRL), the island’s eighth and longest fully underground metro route.
When complete, the US$30bn line will be more than 50km long and will serve the eastern, western and north-eastern corridors by linking Jurong Lake District, Punggol Digital District and Changi.
The project is being built in three phases. The first, lasting around seven years, will cover 29km and will have 12 stations from Aviation Park to Bright Hill. It will interconnect with the East-West, North-East, North-South and the Thomson-East Coast lines.
The LTA is presently issuing tenders for phase two, which comprises six stations from Turf City to Jurong Lake District; engineering studies are in progress on the third phase.
To improve productivity and safety, LTA said it will use a trenchless construction method, which aims to minimise surface settlement during tunnel excavation.
LTA added that it will be exploring other innovative construction methods such as the use of virtual reality, augmented reality and computer simulation tools to “enhance capabilities and facilitate coordination”.
The full CRL is expected to be used by 600,000 passengers daily after the first phase begins operation, increasing to more than 1 million when the entire line is finished.
Related
-
Saudi Arabia qualifies developers for renewable projects
9 January 2026
-
China Railway awarded $272.2 million BNW developments project
9 January 2026
-
Consultant appointed for Qatar-Bahrain causeway study
7 January 2026
-
Vestas gets 390MW wind turbine order in South Korea
5 January 2026
-
Bangladesh seeking contractors for 220 MW solar project
5 January 2026
-
Webuild won €660 million Naples Metro Line 10 in Italy
2 January 2026


京公网安备
11010802030424号
京ICP备19046776号-2