CMEC commissions 810 MWs PTPL power plant in Jhang
6 August 2022
The China Machinery Engineering Corp. (CMEC) successfully commissioned two gas turbines (405 MWs each) of the Punjab Thermal Power Ltd. (PTPL) power plant in the Jhang district.
“We have started simple-cycle commercial operations from the two RLNG-based gas turbines of total 810 megawatts capacity”, PTPL said on Thursday. Work on the 443 MWs steam turbine is also underway at fast pace to achieve the combined-cycle commercial operations, it added.
CMEC executed the project as the EPC (Engineering, Procurement and Construction) contractor. PTPL has also signed an agreement with CMEC for operating the two gas turbines until the steam turbine is put into commercial operations, after which the two parties will renew the agreement to include the combined-cycle operations as well, an official of the CMEC explained.
Work on the steam unit is almost complete but will take around six more months in achieving commercial operations due to complicated pre-commissioning procedures including chemical cleaning of the boiler, the official said. The plant has a total combined-cycle capacity of 1242 MWs.
Related
-
Updated cost estimate for the Snøhvit Future project
18 November 2026
-
CO₂ research project “catch4climate” officially inaugurated with 200 guests from politics and industry
18 November 2026
-
LA ABC, GOBERNACIÓN Y TRANSPORTE ACUERDAN REINICIAR TRABAJOS DE SELLADO DE JUNTAS, BERMAS Y MANTENIMIENTO CONSTANTE EN EL DESVÍO PARA REACTIVAR LA DOBLE VÍA ORURO – CHALLAPATA
18 November 2026
-
Webuild: first span being raised for Vallone delle Coste Viaduct on Ragusa-Catania Highway
18 November 2026
-
OMV receives EUR 450 mn loan from the European Investment Bank for its 140 MW green hydrogen production facility
17 November 2026
-
OMV Petrom: Progress on the Neptun Deep project: the offshore production platform has been installed in the Black Sea
17 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2