The China Machinery Engineering Corp. (CMEC) successfully commissioned two gas turbines (405 MWs each) of the Punjab Thermal Power Ltd. (PTPL) power plant in the Jhang district.
“We have started simple-cycle commercial operations from the two RLNG-based gas turbines of total 810 megawatts capacity”, PTPL said on Thursday. Work on the 443 MWs steam turbine is also underway at fast pace to achieve the combined-cycle commercial operations, it added.
CMEC executed the project as the EPC (Engineering, Procurement and Construction) contractor. PTPL has also signed an agreement with CMEC for operating the two gas turbines until the steam turbine is put into commercial operations, after which the two parties will renew the agreement to include the combined-cycle operations as well, an official of the CMEC explained.
Work on the steam unit is almost complete but will take around six more months in achieving commercial operations due to complicated pre-commissioning procedures including chemical cleaning of the boiler, the official said. The plant has a total combined-cycle capacity of 1242 MWs.
Related
-
Repsol and Masdar to partner in €849 million renewables portfolio in Spain
12 June 2026
-
Turkey plans electricity corridor to supply Europe
10 June 2026
-
Namibia approves Chinese investment in Etango uranium project
9 June 2026
-
11 bids for 90km of roads linking new Polish airport
3 June 2026
-
Morocco awards $1.5bn waste-to-energy contract
2 June 2026
-
China offers to build modular nuclear reactor in Serbia
1 June 2026


京公网安备
11010802030424号
京ICP备19046776号-2