Webuild lifts deck of Europe’s second longest suspension bridge
9 June 2022
In a complex, water-based operation, a Webuild-led construction joint venture has hoisted most of the steel deck of continental Europe’s second longest suspension bridge, which will cross the Danube at Braila in Romania.
The 1,975m-long Braila Bridge, located 8km from the busy port city of the same name, will allow 7,000 vehicles to cross the Danube a day in just two minutes rather than the usual 45-minute ferry trip.
The Webuild JV has completed the operation to lift 62 of the 86 prefabricated segments that comprise the 1,120m-long deck, meaning the bridge is now 67% complete, Webuild said.
Each segment weighs some 260 tonnes, measuring 25m wide, 32m long and 3.2m deep. They were manufactured in a factory 7km away along the river, crane-loaded onto barges and shipped to the bridge to be lifted into their final position on permanent hangers.
Commissioned by state company CNAIR on behalf of Romania’s Ministry of Infrastructure, the bridge will have four lanes, an emergency lane, and cycling and pedestrian paths.
It also has two lateral spans 490m and 365m long, respectively, and an access viaduct 90m long on each side.
A network of roads for a combined 23km is also being developed. Approximately 1,350 workers and 100 direct suppliers are involved in the project.
Related
-
Ecuador plans 2.1 GW power auction with high share of solar
12 January 2026
-
Consultant appointed for Qatar-Bahrain causeway study
7 January 2026
-
Webuild won €660 million Naples Metro Line 10 in Italy
2 January 2026
-
Hidroelectrica to set up joint venture with EDF for 1 GW pumped storage project
1 January 2026
-
New $2.1bln road development projects to ease congestion in Riyadh
1 January 2026
-
Romania’s Electrica opens two solar tenders
31 December 2025


京公网安备
11010802030424号
京ICP备19046776号-2