$720 million! CHEC signs artificial island project with the Philippines
19 January 2022
Recently, China Harbour and the owner of the reclamation project in Pasay City, Philippines (SM Smart City Construction and Development Company) reached an agreement on the sand source and construction period of the project, and signed a supplementary agreement.
The construction period was changed from 730 days for island A and 1,095 days for island B and C to 1,155 days for island A and 1,520 days for island B and C in the original full contract.
The Pasay Reclamation Project is adjacent to the commercial center of Metro Manila and forms three artificial islands with a land area of 360 hectares in Manila Bay. The main work includes foundation trench excavation, bank protection, draught filling, foundation treatment and other construction.
This project is currently the largest dredging and reclamation project in the Philippines, and it is also the largest project won by China Harbour in the Philippine market.
Related
-
Sungrow to supply PV inverter solutions for San Martín project in Peru
24 November 2025
-
Malaysian firm wins $93m Medina residential project
24 November 2025
-
Hyundai begins work on hydrogen fuel cell plant in Korea
21 November 2025
-
Indian firm wins Oman chemicals project EPC contract
20 November 2025
-
SEPCO3 and LonGi awarded 1.5GW Khazna Solar PV Project in Abu Dhabi
18 November 2025
-
One of Greece’s largest BESS projects moves ahead with Trina Storage
18 November 2025


京公网安备
11010802030424号
京ICP备19046776号-2