Australia’s West Gate Tunnel project agreement reached
6 January 2022
An agreement over Australia’s West Gate Tunnel project in Melbourne looks set to allow work to restart. The project ground to a halt when toxic soil deposits were found on the alignment. The need to remove the contaminated ground from the tunnel route for the work to be allowed to continue resulted in a massive jump in costs, triggering a dispute as to who would pay for the removal.
The Victoria State Government and toll road firm Transurban have now agreed terms however. Victoria State is to provide an additional US$1.41 billion (A$1.9 billion) to the works, while Transurban will provide an additional $1.48 billion (A$2 billion). The extra construction costs of $2.52 billion (A$3.4 billion) will be shared between Victoria State and Transurban.
The project is due for completion in 2025 and will now cost a total of $7.42 billion (A$10 billion) instead of the $4.97 billion (A$6.7billion) originally envisaged.
Related
-
Developers appoint contractor for $500m wastewater treatment project
16 February 2026
-
Acciona to build São Paulo road for €334m
14 February 2026
-
Alstom and Terna team win €992m Romania rail contract
14 February 2026
-
VinSpeed teams up with Siemens Mobility for Vietnam high-speed rail project
12 February 2026
-
Axpo, Enhol sign ten-year PPA for 3.7TWh in Spain
12 February 2026
-
Vinci lands €144m Jamaica water job
10 February 2026


京公网安备
11010802030424号
京ICP备19046776号-2