Australia’s West Gate Tunnel project agreement reached
6 January 2022
An agreement over Australia’s West Gate Tunnel project in Melbourne looks set to allow work to restart. The project ground to a halt when toxic soil deposits were found on the alignment. The need to remove the contaminated ground from the tunnel route for the work to be allowed to continue resulted in a massive jump in costs, triggering a dispute as to who would pay for the removal.
The Victoria State Government and toll road firm Transurban have now agreed terms however. Victoria State is to provide an additional US$1.41 billion (A$1.9 billion) to the works, while Transurban will provide an additional $1.48 billion (A$2 billion). The extra construction costs of $2.52 billion (A$3.4 billion) will be shared between Victoria State and Transurban.
The project is due for completion in 2025 and will now cost a total of $7.42 billion (A$10 billion) instead of the $4.97 billion (A$6.7billion) originally envisaged.
Related
-
瓦尔法布里卡项目进入最终阶段:意大利翁布里亚大区完成重大交通导改
17 October 2026
-
BESIX集团升至《工程新闻纪录》(ENR)全球250强国际承包商榜单第44位
17 October 2026
-
BESIX Environment加入欧盟资助项目,在比利时开发可持续PFAS污染治理技术
17 October 2026
-
Recurrent Energy公司西班牙维拉梅卡200 MWp光伏电站投入商业运行
16 October 2026
-
越南维和公司启动投资2900万美元咖啡加工厂项目,优化出口供应链
16 October 2026
-
Samsung C&T Japan Signs MOU with eREX for Collaboration on Renewable Energy Projects
15 October 2026


京公网安备
11010802030424号
京ICP备19046776号-2