Australia’s West Gate Tunnel project agreement reached
6 January 2022
An agreement over Australia’s West Gate Tunnel project in Melbourne looks set to allow work to restart. The project ground to a halt when toxic soil deposits were found on the alignment. The need to remove the contaminated ground from the tunnel route for the work to be allowed to continue resulted in a massive jump in costs, triggering a dispute as to who would pay for the removal.
The Victoria State Government and toll road firm Transurban have now agreed terms however. Victoria State is to provide an additional US$1.41 billion (A$1.9 billion) to the works, while Transurban will provide an additional $1.48 billion (A$2 billion). The extra construction costs of $2.52 billion (A$3.4 billion) will be shared between Victoria State and Transurban.
The project is due for completion in 2025 and will now cost a total of $7.42 billion (A$10 billion) instead of the $4.97 billion (A$6.7billion) originally envisaged.
Related
-
World Bank provides $2bn for Turkey railway corridor
25 May 2026
-
King Salman airport selects three contractors for apron ECI
24 May 2026
-
Japanese firm now fifth biggest US housebuilder after $4bn acquisition
22 May 2026
-
Edify reaches financial close on Rio Tinto-contracted solar-BESS parks
22 May 2026
-
ACCIONA is awarded sanitation for 85 municipalities in northeastern Brazil
22 May 2026
-
Engie launches global business services center in Romania
20 May 2026


京公网安备
11010802030424号
京ICP备19046776号-2