NTPC Issues Consultancy Tender for 105 MW and 220 MW of Solar Projects at Shajapur
17 December 2021
NTPC Renewable Energy Ltd. (NTPC REL) has invited bids from consultants to conduct a geotechnical investigation for 105 MW and 220 MW solar power projects at Shajapur Solar Park in Madhya Pradesh.
Bid Submission End Date is 24-Dec-2021 at 03:00 PM and bids will be opened on the same day.
There is no EMD or tender fees. The bid validity period is of 180 days
The work should be completed within six weeks from the date of the letter of award. The consultant will have to pay liquidated damages at 0.5% of the contract value, subject to a maximum of 5% of the total contract value, if the work is not completed within the stippulated time.
NTPC REL has won a capacity of 105 MW worth Rs 2.35 per unit, and 220 MW capacity at Rs 2.33 per unit in the Rewa Ultra Mega Solar’s auction for 450 MW of solar projects at Shajapur Solar Park in Madhya Pradesh.
Related
-
Sungrow to supply PV inverter solutions for San Martín project in Peru
24 November 2025
-
Malaysian firm wins $93m Medina residential project
24 November 2025
-
Novi Sad plans to build waste-to-energy cogeneration plant
24 November 2025
-
ADB approves $330m loans for clean energy transmission in Pakistan
22 November 2025
-
Google plans €5.5bn infrastructure investment in Germany
22 November 2025
-
Hyundai begins work on hydrogen fuel cell plant in Korea
21 November 2025


京公网安备
11010802030424号
京ICP备19046776号-2