Bouygues picked to build 16km rail viaduct for major new Philippines railway
17 December 2020
Bouygues Construction subsidiary VSL International is starting work on a 16km-long rail viaduct in the Philippines for a section of the 148km North-South Commuter Railway.
Worth over €100m to VSL, the contract covers the precasting and erection of the bridge’s 4,810 segments. VSL, which specialises in post-tensioned and cable-stayed concrete structures, will work from a dedicated precast yard covering some eight hectares.
Bouygues said in a press release today that VSL will set up 23 production units to keep pace with the needs of the precast cycles.
The viaduct deck will be constructed span by span using four launching girders at the same time to reduce the construction program.
Onsite works, which will involve more than 500 people at peak periods, will last for 30 months.
Co-funded by the Asian Development Bank and the Japan International Cooperation Agency, the long-planned North-South Commuter Railway will link the new business zone of New Clark City north of Manila to Calamba City south of the capital.
Multiple international contracting teams have won multiple phases of the railway. The one in question was awarded last year to Japan’s Taisei Corporation and the D.M. Consunji, Inc group (DMCI), of the Philippines, and runs from Malolos, north of Manila, to the Tutuban transit hub in the capital, according to a .
Related
-
EDP completes deal for 121 MW wind portfolio in France and Belgium
16 September 2025
-
Philippines updates net-metering rules to ease adoption for 17,000 users
16 September 2025
-
IB Solar plans 4 GW TOPCon cell and module factory in India
16 September 2025
-
SPPC released RFQ for 5300MW solar and wind projects under NREP
16 September 2025
-
Iberdrola to increase stake in Brazilian utility Neoenergia to 84%
15 September 2025
-
$500M financing secured for Oman–GCC electrical interconnection project
15 September 2025