Argentina authorises expansion of Vientos del Atlántico I wind farm to 210.9 MW

26 November 2026
Argentina authorises expansion of Vientos del Atlántico I wind farm to 210.9 MW

Argentina's gas and electricity regulator, the Ente Nacional Regulador del Gas y la Electricidad (ENReGE), has authorised an increase in transmission grid access capacity for the Vientos del Atlántico I wind farm. The site is located in the Mar Chiquita district, in the province of Buenos Aires. Formalised by resolution RESFC-2026-977-APN-DIRECTORIO#ENREGE, the decision raises the wind farm's generation offer from 102.6 MW to 210.9 MW. The text also makes public a request for a Certificate of Public Convenience and Necessity filed by transmission company TRANSBA. Elsewhere in the wind sector, other players are advancing their projects, such as SeaTwirl, which has submitted the basic design of its 2 MW floating wind turbine.

Article 1 of the resolution authorises the increase from 102.6 MW for phase I to 210.9 MW for phases I and II combined. According to the text, phase II accounts for 108.3 MW. The request was filed by TRANSBA at the request of AES Argentina Generación, the controlling company of Vientos del Atlántico I. The wind farm is connected to the Argentine Interconnection System (SADI) at the 132 kV level of the La Armonía transformer station, which falls under TRANSBA's jurisdiction.

Article 2 makes public the certificate request for three expansion works on the electricity transmission network. These works concern the Villa Gesell-Vivoratá high voltage line and the La Armonía transformer station. The new section would use an ACSR-type conductor (aluminium conductor steel reinforced) of 300/50 mm2. The planned works are as follows:

sectioning of the second 132 kV circuit of the Villa Gesell-Vivoratá high voltage line; construction of 3 kilometres of 132 kV double circuit between this line and the La Armonía transformer station; construction at the La Armonía station of two 132 kV bays, one line entry and one line exit, as well as a transformer bay on the 132 kV busbars.

The certificate request is published for five administrative business days on the websites of the Ente Nacional Regulador de la Electricidad (ENRE) and the Compañía Administradora del Mercado Mayorista Eléctrico (CAMMESA). It must also appear for two consecutive days in a widely circulated newspaper in the area where the works will take place or in the area that may be electrically affected. From the last publication, a period of ten administrative business days begins. Any party that considers its electricity services or economic interests affected may then file a written, substantiated objection with ENReGE.

If substantiated objections common to several users are filed, the regulator will convene a public hearing. This hearing would allow the objections to be examined and give the applicant the opportunity to respond. In the absence of such objections, ENReGE will grant the certificate once the deadlines have expired. Authorisation procedures govern energy infrastructure in other sectors as well, as illustrated by Posiva, which has completed a first test transport to its Finnish encapsulation plant.

Articles 6 and 7 of the resolution set out the technical requirements that Vientos del Atlántico I will have to meet. These obligations will apply once the capacity increase has been carried out and the certificate issued. The resolution mentions neither an investment amount nor a commissioning schedule for phase II. Nor does it specify the start date of the grid works.

The authorised scheme combines a 108.3 MW phase II and a 132 kV grid expansion, including 3 kilometres of double circuit. The granting of the certificate remains subject to the outcome of the consultation period. The wind farm, controlled by AES Argentina Generación, is already connected to the La Armonía station operated within TRANSBA's jurisdiction.