Olkaria I Geothermal Power Station: KenGen Injects 63.3MW into National Grid After Upgrade
26 November 2026
Kenya Electricity Generating Company (KenGen) has injected an additional 63.3MW into the national grid. This comes after the company successfully rehabilitated the country’s oldest geothermal power station, Olkaria I.
The power plant, commissioned in 1981, has been undergoing an extensive three-year rehabilitation programme.
The move comes at a time when the country’s power demand has risen sharply against limited production, raising fears of a power crisis in the coming years.
According to KenGen MD Engineer Peter Njenga, before the renovation works began, the facility was generating approximately 45MW.
He said that trials were underway at the plant. The plant will be commissioned by President William Ruto on December 7, 2026.
“We are happy to announce that the rehabilitation works of Olkaria I are now complete. Currently, we have injected an extra 63.3mw into the national grid,” he said.
Njenga was addressing the press in Naivasha after a clean-up ahead of the three-day sustainable energy conference in the geothermal-rich area Olkaria region.
Moreover, he said that the power generating company would use the conference to meet financiers because some of the projects that they intended to embark on required huge resources.
“We are going to tell our financiers the projects that we are embarking on for the next number of years and the resources that we require and demonstrate what we have been able to do,” he said.
On the green energy park in Olkaria, he said that five investors were on the ground, adding that there was enough power supply to meet their demands.
According to Njenga, a fertilizer production company was on the ground, adding that it would require 165mw from geothermal.
“We have enough energy in Olkaria. Also, some of the companies like Kaishan which are producing fertilizer will just require steam from our geothermal fields,” he said.
Related
-
Argentina authorises expansion of Vientos del Atlántico I wind farm to 210.9 MW
26 November 2026
-
Avantus signs PPAs with PG&E for 800 MW of solar in California
26 November 2026
-
Pakistan’s Cnergyico Refinery Upgrade Project Seeks up to $300M in Foreign Financing
26 November 2026
-
BarMar Subsea Hydrogen Pipeline Secures $2.75B Investment for Spain-France Connection by 2032
26 November 2026
-
Equinor and JAPEX agree asset swap on the Norwegian continental shelf
26 November 2026
-
AIS wins contract for cable protection at 390MW Shinan-Ui wind farm
26 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2