Quant trading firm XTX Markets launches 22.5MW data center in Kajaani, Finland
26 November 2026
Algorithmic trading firm XTX Markets has launched its first data center in Kajaani, Finland. Offering 22.5MW, the data center is located on a 193-hectare site and spans 15,000 sqm (161,460 sq ft).
A second data center building is set to go live in 2027. XTX Markets will use the site to power deep learning to analyze large amounts of data and forecast prices for global financial instruments.
The company says this is the first time it will be run on compute housed within its own data center infrastructure. Prior to this, XTX was hosting its compute in data center space leased across Europe.
The company has therefore had to undertake a major migration effort, including physically transporting compute and storage equipment to the new data center without disrupting operations.
In one six-week period, the team moved 417 petabytes of storage capacity. Mike Irwin, COO of XTX Markets, said: "We set an ambitious timetable for our first data center and delivered.
Our second facility is scheduled for completion in 2027, with more planned.
We've already invested over €400 million ($437.73m) in construction, overwhelmingly with Finnish companies, and have ambitions to invest billions more." Irwin went on to criticize the "government bureaucracy and worrying lack of engagement" regarding the expropriation process for grid development.
"Expropriation permits that once took months can now take years. Businesses cannot reasonably be expected to commit billions of euros while leaving critical infrastructure decisions in administrative limbo.
This is not about demanding electricity capacity that doesn't exist.
It's about the government's ability to process applications, make decisions, and engage with investors who are already delivering substantial economic benefits." He concluded that XTX remains committed to Finland for "decades" and that "we remain willing to work with government and industry, including contributing financially to infrastructure solutions that benefit Finland more broadly.
But long-term commitments require long-term certainty, and without meaningful government engagement, future investment decisions will inevitably be called into question." XTX is building a third data center at the campus, but the company said that government expropriation permitting delays mean power availability remains uncertain for the third facility.
Construction will be completed in 2028.
Regarding the efforts to ensure the project does not unnecessarily harm the environment, construction was paused when sand martin nests were discovered, waiting until the nesting period had ended, and during the design of underground cable routes, surveys using a trained detection dog helped identify potential flying squirrel habitats.
Trees were marked for retention, and the cable routes were adjusted to avoid the identified areas. The data center also operates without consuming water for cooling, placing no cooling-related demand on the local water supply.
XTX has also pledged €1.6m ($1.75m) to community initiatives, including community facilities and developing workforce skills and education in the area. The company's plan for the data center was revealed at the start of 2025 .
YIT served as the main contractor. The company and YIT announced plans for and started construction on a second facility later in 2025, and the third was announced in June 2026.
Related
-
AIS wins contract for cable protection at 390MW Shinan-Ui wind farm
26 November 2026
-
NKT begins HVDC cable production for TenneT’s IJmuiden Ver Beta project
26 November 2026
-
Colibri signs LoI to acquire Sonora copper-molybdenum projects
26 November 2026
-
State funding to support geothermal heating in school and daycare in Lahausen, Germany
26 November 2026
-
Three data center projects planned around Phoenix, Arizona
26 November 2026
-
Promera acquires Irish electrical contractor B&G to expand data center offering
26 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2