Three data center projects planned around Phoenix, Arizona
26 November 2026
Three new large-scale data center projects are planned around Phoenix, Arizona.
Fortescue looks to build data centers in Buckeye First reported by Azbex , Phoenix Hydrogen Hub LLC is requesting a Conditional Use Permit (CUP) with the City of Buckeye for a data center campus on approximately 157 acres located west of the northwest corner of State Route 85 and Patterson Road.
Located close to the planned Woolsey Peak substation to the east of Phoenix, the property is currently zoned Heavy Industrial (I-2).
The proposed development includes three 100MW data center buildings, an approximately 300MW natural gas-fired generating plant, and battery energy storage systems (BESS).
The development is known as the Buckeye Energy Campus and would total 1.725 million sq ft (162,766 sqm).
The project would initially utilize 120MW of electricity supplied by Arizona Public Service (APS), with future on-site natural gas generation intended to serve the data center campus.
The project would utilize closed-loop cooling systems to reduce water use.
Located at 28400 W Patterson Road and historically used for agricultural purposes, the site was originally rezoned for a hydrogen gas production facility that was canceled last year.
Australian energy and metals company Fortescue is behind the Phoenix Hydrogen LLC.
Southwest Crossing Phase II comes to Eloy In Eloy, CRG, the real estate development arm of Clayco, has requested an Amendment to the Zoning Map (Rezone) to rezone approximately 152 acres on the northwest Corner of Tweedy & Battaglia Roads from Light Industrial (I-1) to I-2 General Industrial Planned Area Development Overlay (PAD) to allow for data center development.
The 400MW, 1.2 million sq ft (111,483 sqm) project is known as Southwest Crossing Phase II. Up to seven two-story data center buildings, approximately 160,000 square feet (14,864 sqm) each, are planned, as well as an on-site substation.
Phase I of the project was approved last year. That part is also set to include seven buildings and an on-site substation. Eloy is a city in Pinal County, around 50 miles (80.4km) southeast of Phoenix. The Loretta J.
Haugen Trust is listed as the property owner.
Casa Grande could bring PhoenixMart back to life AZ Sourcing LLC and Phoenix Mart LLC are seeking to amend a portion of a previously approved Planned Area Development into the Casa Grande Tech Center.
The campus would be located on more than 230 acres south of Florence Boulevard and west of Interstate 10 in Casa Grande. On-site power generation via natural gas and battery energy storage are planned. Rooftop solar is also planned.
The property is zoned Industrial (I-2), where data centers are an allowable use subject to approval of a Conditional Use Permit.
The site was previously earmarked for PhoenixMart, a 1.5-million-square-foot (139,354 sqm) commercial trade and wholesale hub first proposed in 2011 but never brought to fruition.
A large empty shell building was built and would be reused as a data center. According to a government announcement , no specific end user or data center operator has been identified at this time.
Casa Grande is located around 50 miles (80.4km) southeast of Phoenix in Pinal County, close to Eloy. Another large-scale project is planned in the area.
The City of Casa Grande Planning and Zoning Commission approved a Conditional Use Permit (CUP) for the proposed 954-acre Grande Valley Data Center campus at its October 1 meeting.
The project is located south of Montgomery Road and Maricopa-Casa Grande Highway.
Related
-
State funding to support geothermal heating in school and daycare in Lahausen, Germany
26 November 2026
-
Quant trading firm XTX Markets launches 22.5MW data center in Kajaani, Finland
26 November 2026
-
South African gov't floats converting old power stations into data centers
26 November 2026
-
Blackstone's Link Logistics eyes data center outside Minneapolis, Minnesota
26 November 2026
-
350MW data center campus proposed in New South Wales, Australia
26 November 2026
-
Fluidstack launches modular data center product, Blackbird
26 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2