SOSA Energy Center Secures $78M Financing for 150 MW Texas Battery Storage Project
24 November 2026
Energy Vault Holdings, Inc., a global energy infrastructure company supporting grid reliability and next-generation AI and high-performance computing infrastructure, has announced the closing of $78 million in construction and bridge financing for the SOSA Energy Center (“SOSA”), its 150 MW / 300 MWh battery energy storage system (“BESS”) in Madison County, Texas. Furthermore, the bridge financing will be repaid with the already committed $80 million preferred equity investment on project completion. Together, the construction financing, the preferred equity investment, and draw on the OIC preferred facility are intended to support SOSA through construction and into commercial operation on a non-recourse basis. Moreover, this project alongside others show how Texas emerges as a leading energy hub in the US.
Additionally, SOSA was the first energy storage asset formally acquired and placed into development under Asset Vault. This is the Company’s platform dedicated to owning and operating energy storage and AI infrastructure assets. Once complete, SOSA will operate in the ERCOT North market on a merchant basis. Additionally, it will have the flexibility to enter a contracted offtake agreement as market conditions evolve.
Construction Start Date and Key Timelines
Construction at SOSA began in the fourth quarter of 2025, with site control and environmental and interconnection milestones in place. Since then, civil work has been completed. Additionally, a substation has been installed, with Energy Vault self-performing engineering, procurement and construction. Also, major equipment is expected on site in the coming months ahead of commercial operation expected in 3Q27.
“Storage earns its place in a portfolio the way any infrastructure does, by being financed on its fundamentals,” said Cory Magnuson, President of Asset Vault at Energy Vault. “A bank, a strategic partner and an institutional investor have each backed SOSA on those terms. Furthermore, SOSA Energy Center reinforces our Asset Vault strategy of building projects that generate recurring revenue, robust EBITDA margin. Also, it reinforces long-term operating cash flows.”
Construction at SOSA began in the fourth quarter of 2025.
Lastly, the SOSA Energy Center represents an approximately $100 million investment in Madison County. Also, it is estimated to generate $9.3 million in tax revenue for North Zulch ISD and Madison County over a 10-year period. Moreover, construction is also expected to create 65 jobs in the local community.
Related
-
Seismic survey for geothermal exploration starts in Nuremberg, Germany
24 November 2026
-
Argentina LNG Project Targets 2031 Exports Following US$50.75 Billion RIGI Approval
24 November 2026
-
Global Insurance Coverage Secured for Doosan Enerbility Turbine-Deployed Yawol Offshore Wind Farm
24 November 2026
-
CtrlS moves forward with 150MW data center project in Bihar, India
24 November 2026
-
PPC highlights progress on Western Cape integrated cement plant
24 November 2026
-
Masterise proposes $693 mln budget increase, master plan revisions for Gia Binh international airport
24 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2