Masterise proposes $693 mln budget increase, master plan revisions for Gia Binh international airport
24 November 2026
Masterise Aviation Infrastructure JSC (MAI), the investor behind Gia Binh International Airport in northern Vietnam, has proposed increasing the project's total investment by nearly VND17.87 trillion ($693 million) to VND214.24 trillion ($8.31 billion), alongside changes to its runway system, cargo terminal layout, and transport connections.
The company has requested the Ministry of Construction’s approval of adjustments to the airport’s master plan for 2021-2030, with a vision to 2050.
Located across Gia Binh, Luong Tai, Nhan Thang, and Lam Thao communes in Bac Ninh city, Gia Binh International Airport is planned to meet the International Civil Aviation Organization’s (ICAO) 4F standards.
The National Assembly previously approved an investment of VND196.37 trillion, comprising VND141.23 trillion ($5.48 billion) for the period through 2030 and VND55.14 trillion ($2.14 billion) for the period through 2050. The project will be funded by the investor through equity and other legally mobilized capital.
Under the newly submitted proposal, the developer seeks to raise the total capital outlay across both development phases to VND214.24 trillion ($8.31 billion). Capital allocation through 2030 would increase to VND161.55 trillion ($6.26 billion), while the amount for 2031-2050 would be revised down to VND52.69 trillion ($2.04 billion).
An initial illustration of Gia Binh International Airport in Bac Ninh city, northern Vietnam. Photo courtesy of Masterise.
Runway and cargo terminal plans revised
Under the existing master plan, the airport would have two runways measuring 3,500 meters and 4,000 meters in the 2021-2030 period, with two additional runways of 3,500 meters and 3,650 meters planned by 2050.
The proposed adjustment would retain the four-runway configuration but revise their lengths. By 2050, the two northern runways would each measure 3,500 meters, while the southern pair would comprise one 4,000-meter runway and one 3,650-meter runway. The changes are based on the planned land area and projected cargo demand.
The number of rapid-exit taxiways connecting runway No. 3 to the parallel taxiway would increase from four to five.
The aircraft parking layout would also be adjusted to improve passenger access to the terminals. The airport is expected to have 83 parking positions by 2030, serving the VIP terminal, passenger terminal, cargo terminal, and maintenance area. This number would rise to 123 by 2050.
Another major change is adding a western cargo terminal to complement the eastern cargo terminal in the existing plan. The additional facility is intended to accommodate rising air freight demand.
Rail and highway connections expanded
The tailored plan also seeks to strengthen the airport’s links with national, regional, and provincial transport networks, including highways, conventional railways, high-speed rail, and urban rail systems.
Planned road connections include the Hanoi-Lang Son, Hanoi-Thai Nguyen, Hanoi-Hai Phong-Quang Ninh, and Hanoi-Bac Ninh-Ha Long expressways. The capital region’s Ring Road 4 is identified as a key corridor linking the airport with central Hanoi and Hai Phong.
The proposal also adds an expressway connecting Hanoi to Hai Phong via Gia Binh, aiming to shorten travel times for passengers and cargo moving between major economic hubs in northern Vietnam.
For rail connections, the airport is expected to link with the Hanoi-Hai Phong railway, the Hanoi-Quang Ninh high-speed railway, and urban rail lines from Hanoi and Bac Ninh.
The proposed location of the airport’s urban railway station would also change. Instead of entering the center of the passenger terminal, the line would run alongside it, with plans for a future connection to Bac Ninh city. Under this arrangement, passengers would walk 400 meters to reach check-in counters.
Gia Binh is envisioned as a smart, green and sustainable international airport, serving both civilian and military purposes. The project also aims to achieve a five-star rating under Skytrax standards and become a major aviation gateway for northern Vietnam, handling passenger and cargo transit as well as aircraft maintenance for the Asia-Pacific region.
The airport is designed to handle 30 million passengers and 1.6 million tons of cargo annually by 2030. By 2050, its planned capacity would increase to 50 million passengers and 2.5 million tons of cargo a year.
Related
-
Seismic survey for geothermal exploration starts in Nuremberg, Germany
24 November 2026
-
PPC highlights progress on Western Cape integrated cement plant
24 November 2026
-
Details shared of AWS' 300MW data center in Kozani, Greece
24 November 2026
-
Niron Magnetics Plans $1.8B Rare-Earth-Free Magnet Campus in Dothan
24 November 2026
-
Pertamina begins FEED phase for Lumut Balai 3 geothermal power plant in Indonesia
24 November 2026
-
Northern Europe Energy eyes 200MW data center project outside Riga, Latvia
24 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2