Saudi Arabia expands self-consumption rules to 50 MW

24 November 2026
Saudi Arabia expands self-consumption rules to 50 MW

The state-owned Saudi Electricity Regulatory Authority (SERA) has updated its rules for renewable energy generation facilities designed for self-consumption.

The regulation covers renewable power systems, including solar, wind, waste-to-energy and biofuel installations, at homes and other buildings that are designed to meet consumers’ electricity needs. It stipulates that generation and consumption must take place at the same facility and permits integrated battery storage systems.

A statement published by the Saudi Press Agency says the new rules aim to improve installation, connection and operation procedures while clarifying requirements for consumers, enhancing safety and efficiency, and protecting consumer rights.

The updated regulation raises the maximum generation system capacity covered by the framework from 2 MW to 50 MW. Grid-connected systems are now divided into four categories: 1 to 11 kW, above 11 kW to 50 kW, above 50 kW to 2 MW, and above 2 MW to 50 MW.

Systems in the first category, typically residential-scale installations, require no prior approval before installation but must be notified to the service provider and installed by an accredited contractor. There is no connection fee for this category.

The second category, covering systems above 11 kW to 50 kW, requires an accredited contractor and a feasibility study and is subject to an application or connection fee of SAR 700 ($186.95). Systems above 50 kW to 2 MW require an accredited consultant or contractor, as well as a network impact assessment, and are subject to a SAR 2,300 fee.

Systems in the final category, above 2 MW to 50 MW, require a study permit and a generation license from SERA. The application or connection fee is set at SAR 16,500 for systems between 2 MW and 4 MW, increasing to SAR 35,000 for systems above 4 MW.

The regulation requires service providers to process connection requests in the order they are submitted via an electronic platform. Providers are also required to publish a list of qualified contractors and approved equipment, as well as details of available network capacity.

The regulation also sets out a framework for mandatory net billing, under which surplus electricity exported to the grid is credited financially.

Credits are carried forward to the next billing cycle, where they can be deducted from electricity charges. The framework says credits can be used across multiple accounts, provided the accounts belong to the same consumer, and are valid for 12 months from accrual.

SERA’s updated framework comes three years after it first issued regulations for renewable energy self-consumption. It also consolidates two existing regulatory frameworks for renewable energy self-consumption and small solar energy systems.

Saudi Arabia installed around 7.8 GW of solar last year, taking cumulative capacity to around 12.4 GW.