Indonesia could reach 96.7 GW of solar by 2029 with policy reforms
20 November 2026
Indonesia’s cumulative installed solar capacity reached 1.59 GW as of the first quarter of 2026 (Q1 2026), according to the latest report from the Institute for Essential Services Reform (IESR), a Jakarta-based think tank.
IESR’s Indonesia Solar Energy Outlook 2027 says the figure is equivalent to around 1.5% of Indonesia’s power generation capacity and 0.3% of electricity production.
Rooftop PV currently accounts for the largest share of installed capacity, standing at 0.9 GW as of Q1 2026. Utility-scale solar accounted for 0.33 GW, captive solar for 0.3 GW and installations in remote areas for around 0.06 GW.
With the country passing the 1 GW solar milestone in 2025, IESR says the current growth rate is “far behind the government’s ambition to make solar power one of the backbones of the national energy system”, as set out in the country’s 100 GW solar power program which President Prabowo Subianto has set a target of achieving by 2029.
The program officially launched in August with a first phase of 14 projects totalling around 5.2 GW, but only 526 MW of this capacity currently have targeted completion dates, IESR’s report reveals.
The think tank adds that deployments are currently held back by regulatory gaps, procurement uncertainty and limited grid access.
IESR CEO Fabby Tumiwa said the 100 GW ambition needs to be reflected in updates to Indonesia’s 2025-2034 electricity supply business plan (RUPTL), with greater emphasis on utility-scale PV and battery energy storage systems (BESS), diesel replacement with solar-plus-storage and rooftop PV deployment.
IESR’s modelling suggests Indonesia could reach 96.7 GW of solar capacity by 2029 if development proceeds through multiple channels simultaneously.
The report says around 8 GW is already planned through RUPTL and Mentari GigaOne procurements, while a further 56 GW could come through procurements by Indonesia’s state-owned electric utility PLN. It suggests the remaining 33 GW could be developed through rooftop PV, diesel replacement, rural electrification, captive solar and other distributed applications.
IESR says five enablers that must move together – demand, rooftop access, procurement, grid and supply chain – will determine whether the 100 GW scales.
Under a high-electrification scenario, Indonesia’s electricity demand could be around 160 TWh higher in 2035 than under a business-as-usual scenario, according to figures from the report. Electrification of transport, industry, cooling, cooking and data centers, alongside potential electricity exports, could help create additional demand for solar generation.
IESR also suggests rooftop solar quotas be determined according to grid hosting capacity at the substation level, rather than through the current quota system, which it said limits deployment.
For utility-scale projects, the report recommends more transparent procurement schedules and reverse auctions. Projects are frequently tendered individually without a clear timetable, making it harder for developers, lenders and suppliers to prepare, IESR said.
Grid and storage investment will also need to keep pace. Indonesia’s 2025-2034 RUPTL includes 42.6 GW of renewable energy and 10.3 GW of energy storage, but some transmission infrastructure needed to integrate solar is not scheduled until 2030-2034. IESR’s report recommends regulatory changes and incentives to encourage investment in storage.
In the report, Tumiwa notes that Indonesia’s domestic solar supply chain is rising faster than demand. Solar module production capacity reached 27 GW per year in 2026, although the report notes more than half of it needs further verification due to relabelling allegations, while cell capacity now stands at 14.3 GW.
It says that after 98.2% of Indonesia’s solar module exports went to the United States in 2025, US preliminary duties of about 104% in February 2026 cut Indonesian exports to the US by about 98%, from a peak of 2.2 GW in November 2025 to 34 MW in April 2026. Final duties of up to 268% followed in September 2026
IESR says the 100 GW programme “could provide a market anchor [for the solar supply chain] if accompanied by consistent policy and project certainty”.
The 100 GW target must also be explicitly incorporated into revisions of the National Electricity General Plan (RUKN) and RUPTL, IESR added, with defined procurement channels, grid requirements, distributed solar roles and legal frameworks for project ownership and financing.
Related
-
Ports Regulator’s integration into emerging Transport Economic Regulator targeted for January 2027
18 November 2026
-
Italy surpasses 1 million renewable-linked battery storage systems
18 November 2026
-
Poland awards 1.81 GW of solar in latest renewables auctions
18 November 2026
-
Vietnam’s energy security under pressure as net energy imports near 44%
17 November 2026
-
Reservas probadas de gas natural en Bolivia caen a 2,3 TCF, el más bajo nivel registrado en dos décadas
17 November 2026
-
Gobierno autoriza importación excepcional de Gas Natural y Gas Natural Licuado a privados para consumo propio y generación eléctrica
17 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2