Bahrain tenders 100MW Bilaj Al-Jazayer solar project
12 November 2026
Bahrain’s Electricity and Water Authority (EWA) has issued a tender for the Bilaj Al-Jazayer independent power project (BAJ solar IPP), a utility-scale solar scheme with a planned capacity of at least 100MW.
The project will be procured on a public-private partnership basis using a build-own-operate (BOO) model.
The selected developer will develop, finance, design, construct, operate, maintain, decommission and restore the project site over a 25-year contract period.
EWA has set a target commercial operation date of 31 December 2028.
The scope includes photovoltaic generation facilities, utility-scale inverters, access roads and internal roads. The plant will use proven photovoltaic modules and inverters designed for Bahrain’s local operating conditions.
The tender was published on 8 November. Companies have until 20 December to submit bids, with bid opening scheduled for 21 December.
The tender requires an initial bond of BD300,000 ($796,000).
The project will be awarded through a single-stage request-for-proposals process.
Bidders will first be assessed against minimum eligibility requirements covering financial strength, project-financing capability and experience in large-scale solar developments before their technical and financial proposals are evaluated.
A single bidder must demonstrate tangible net worth of at least $50m.
In a consortium, each member must demonstrate net worth equivalent to its proposed shareholding in the $50m threshold, while the managing member must have a tangible net worth of at least $20m.
The managing member must also have secured at least $150m of limited-recourse financing across three or more infrastructure projects during the past 10 years. It must hold at least a 15% equity stake in each reference project.
Bidders or their engineering, procurement and construction contractors must demonstrate experience delivering either three grid-connected ground-mounted solar projects of at least 100MWac each globally, or two projects of at least 70MWac each in the GCC. The reference projects must be connected to the grid at 66kV or above.
The BAJ solar IPP supports Bahrain’s target of sourcing 20% of its energy from renewable sources by 2035.
Related
-
DXN signs Pacific CLS contract with unnamed Internet company
12 November 2026
-
EBRD plans to invest US$ 6 billion in Türkiye’s REACT projects over the next five years
12 November 2026
-
UK Unveils £12 Billion Offshore Wind Investment for 2.8GW Norfolk Projects Ahead of COP31
12 November 2026
-
$1bn King Fahd Stadium Upgrade Advances Ahead of Saudi Arabia’s 2034 World Cup Preparations
12 November 2026
-
Terex to acquire Keestrack
11 November 2026
-
Kazakhstan plans first SAF plant with annual capacity of 57,000 tons
11 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2