Saudi water sector hits sharp slowdown

9 September 2026
Saudi water sector hits sharp slowdown

Saudi Arabia’s water sector has recorded a sharp slowdown in contract awards this year, with $3.94bn of new contracts awarded as of early September.

According to regional project tracker MEED Projects, this is well below the $10.7bn recorded in 2025, $13bn in 2024 and a record $15.3bn in 2023.

The slowdown comes as several major projects remain in the procurement process, with some yet to reach financial close or contract award, while tender deadlines for other schemes have been pushed back.

Among the largest is the estimated $2bn Riyadh‑Qassim independent water transmission pipeline. The 859‑kilometre project will have a transmission capacity of 685,000 cubic metres a day (cm/d). Vision Invest was selected as the preferred bidder last December; however, more than eight months later, an official developer’s agreement has not yet been signed.

Similarly, the Arana and Hadda independent sewage treatment plant (ISTP) projects have yet to reach the financial close originally targeted for the second quarter. The two schemes will provide a combined treatment capacity of 350,000 cm/d.

Delays extend further down the procurement pipeline. The latest developer bid deadline for the estimated $150m Riyadh East ISTP is 29 September, almost a year after the request for proposals (RFP) was issued in October 2025.

Procurement for the main contracts for the Jubail‑Buraidah and Ras Mohaisen‑Baha‑Mecca independent water transmission system projects could also slip into 2027, amid delivery‑model changes by Water Transmission Company.

New awards

The market received a boost in September when Saudi Arabia’s National Water Company (NWC) announced it had signed a SR1.3bn ($347m) deal with a Saudi‑Chinese consortium for package 10 of its long‑term operations and maintenance programme.

The consortium – comprising China’s Jiangsu United Water Technology and Saudi‑based Armada Holding – will rehabilitate, operate and maintain nine sewage treatment plants (STPs) with a combined design capacity of more than 337,000 cm/d. Based on the latest procurement timeline, it is unclear whether the selected consortium for package 11 will be formally announced this year. Packages 12 and 14 remain under tender while package 16 is next in line, with its RFP not expected to be issued before November.

NWC is the second‑largest awarding entity by value in 2026, accounting for $1.09bn, or about 28% of the total. Saudi Aramco is the largest, with $2.15bn, meaning the two organisations account for more than 82% of awards so far this year.

Saudi water contract awards in 2026 by owner ($m)

National Water Company1,088
Royal Commission for Jubail & Yanbu133
Royal Commission for Riyadh City50
Saudi Arabian Mining350
Saudi Aramco2,150
Saudi Water Authority41
Sharakat / National Centre for Privatisation & PPP132

Aramco’s activity has been led by two major oil field developments. In June, it awarded the $1.5bn Safaniya onshore surface facilities project: package 1 to a joint venture of Tecnimont and Consolidated Contractors Company. The package includes a water treatment and injection plant supporting upstream production.

It also awarded the second phase of its Zuluf water treatment project to a joint venture of Almar Water Solutions and AlJomaih Energy & Water. The project will add a 308,000‑cm/d treatment facility at Tanajib in the Eastern Province, supplying water for injection at the offshore Zuluf oil field.

The concentration of awards in industrial projects this year has been notable. Against the slowdown in municipal water infrastructure procurement, much of the value awarded so far has been linked to the water requirements of oil and gas and mining developments.

The third‑largest award is the $350m Taif Ar Rjum water pipeline project, being developed by Saudi Arabian Mining Company (Maaden) in Mecca. The project will support the Ar Rjum gold mining and processing facility and is being developed under a build‑own‑operate‑transfer model.

By project type, treatment projects make up the largest share of awards, at $2.85bn or about 72% of the total. Transmission projects account for $980m and cooling projects for a further $110m, while no major desalination or water storage contracts have been awarded so far this year.

Contract awards in Saudi Arabia’s water sector, 2017‑26 ($m)

2017201820192020202120222023202420252026
Cooling2912040080650160444110
Desalination4201,0163,2532,8231,4958641,3721,3662,178
Storage23522390586041,8131,0361,699268
Transmission1,5023,0131,9697834,9553,43910,6765,6636,879980
Treatment1741,4838153271,3071,3682,0573,8271,3902,854
Total2,3605,8556,1274,3918,4418,13415,30112,99910,7153,944

Project pipeline

The slowdown in awards appears to reflect the timing of projects moving through procurement rather than a fundamental weakening in demand for water infrastructure.

Saudi Arabia continues to face rising demand for desalination, wastewater treatment and water transmission as population growth and industrial expansion drive demand for water.

Sharakat, formerly Saudi Water Partnership Company, set out the next phase of the kingdom’s water investment programme in its latest seven‑year statement, published in March.

The plan points to a significant expansion in desalination capacity. Capacity from Sharakat‑procured projects is expected to increase from about 3.88 million cm/d in 2025 to roughly 7.18 million cm/d by 2031.

The increase will be supported by seven new independent water plants (IWPs) with a combined capacity of about 2.8 million cm/d, in addition to projects already operating, under construction or in procurement.

However, several of the planned projects have yet to move into active procurement, while others have seen their expected timelines pushed back.

Among the schemes affected are the Ras Al‑Khair, Tabuk, Shuqaiq and Jizan IWPs, which have all progressed through prequalification, but have seen changes to their expected procurement schedules.

The largest is phase two of the Ras Al‑Khair IWP, a 600,000‑cm/d reverse osmosis desalination plant that has been in development for more than a decade.

The revised schedule indicates that the $400m Al‑Shuqaiq 4 IWP is expected to be the first of the seven new plants to reach commercial operation. Its main contract had been expected to be tendered later this year, but it is now understood that the first RFP will not be issued until early 2027.

to
TOP