Wärtsilä to supply 412MW of engine power for US data centre
20 April 2026
Wärtsilä has secured a contract to supply 412MW of engine power for a new hyperscale data centre project in Ohio, US.
The project will feature the deployment of 40 Wärtsilä 34SG spark gas engines.
According to Wärtsilä, this is the first instance of the 34SG model being used in a data centre context.
With this latest contract, the company’s total engine capacity sold into the US data centre market surpasses 1.6GW.
Wärtsilä booked the order in the second quarter of 2026 (Q2 2026).
The new Ohio power plant will be capable of providing flexible, primary power to the data centre, supporting operations without reliance on the local power grid.
This approach aims to address the lengthy grid interconnection wait times that are often faced in the US.
The company plans to deliver the equipment in line with expectations for the data centre to begin commercial operations in early 2028.
This project marks the fourth order Wärtsilä has received for data centre power solutions in the US.
The modular configuration of the 34SG engines enables data centre developers to add capacity in discrete blocks, with the potential for scaling to more than 500MW.
Globally, Wärtsilä Energy reports a track record of supplying 81GW of power plant capacity and more than 130 energy storage systems in 180 countries.
Wärtsilä Energy Americas vice-president Risto Paldanius said: “As AI and cloud demand accelerate, operators need energy solutions that are efficient, resilient and available on their timeline – not the grid’s. Wärtsilä provides that foundation, delivering dependable, high-performance power that scales as quickly as their infrastructure.
“The customer chose Wärtsilä for its proven reliability, rapid deployment and strong operational efficiency across diverse operating conditions.”
In January, Wärtsilä received an order to deliver 429MW of engine power to a US power plant to address growing data centre demand.
The facility, operated by an investor-owned utility, will be equipped with 24 Wärtsilä 50SG engines under a contract recorded in Q1 2026.
Related
-
Ahold Delhaize and Rezolv Energy sign ten-year virtual PPA
7 November 2026
-
Ignitis starts operations at 173.6MW Tume solar farm in Latvia
7 November 2026
-
Alternergy Energizes 64 MW Alabat Wind Farm in the Philippines Ahead of Amihan Season
6 November 2026
-
Exergy to supply 33-MWe Maren Maras geothermal power plant in Aydin, Türkiye
6 November 2026
-
$1.39bn Ruwais Terminal Ammonia Financing Advances Two Major Construction Projects in Abu Dhabi
6 November 2026
-
Fluor to proceed with Sierra Gorda grinding line project in Chile
5 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2