Construction begins on Russia’s largest wind farm
29 November 2024
A division of Russian engineer Rosatom has begun work on a 300MW wind farm in the Republic of Dagestan in the northern Caucasus.
The project will be carried out in two phases, the first of which involves the installation and commissioning of 61 turbines with a capacity of 152MW. This is due to be completed next year.
Fifty-nine units will be installed in the second phase, and will begin operations in 2026. When that happens, the Novolakskaya wind farm will generate 879 GW/h of energy a year.
At present, 190 workers are present at the site in the Kumtorkalinsky, where they are installing foundations and creating access roads. A plant capable of mixing 140 cubic metres of concrete an hour is operating at the site.
Sergei Nazarov, the Russian Federation’s deputy minister for economic development, said in a press statement that the plant would be a “breakthrough” project and would promote the “social and economic development of the North Caucasus Federal District”.
He said: “I would like to note that the wind farm will allow the creation of additional generation in the Novolaksky District, providing a source of environmentally friendly energy to stabilise the grid voltage, improve robustness of power supply to the population and offer the opportunity of economic and social development of the territory."
Related
-
Montenegro’s power utility EPCG, Masdar sign cooperation agreement
16 January 2026
-
Engie wins SECI bid for 200MW solar PV-600MWh battery project in India
15 January 2026
-
Ecuador plans 2.1 GW power auction with high share of solar
12 January 2026
-
Montenegro gets €175m from EU to modernise rail
11 January 2026
-
Cimic wins Indonesia energy infrastructure job
10 January 2026
-
Saudi Arabia qualifies developers for renewable projects
9 January 2026


京公网安备
11010802030424号
京ICP备19046776号-2