Oman achieves 60pc Implementation of Manah 1, Manah 2 Solar Power Projects
15 July 2024
Nama Power and Water Procurement Company, Oman announced that it achieved 60 percent implementation of Manah 1 and Manah 2 solar energy projects in the wilayat of Manah, A’Dakhiliyah Governorate.
The electricity generation projects, whose lumpsum cost stands at about $800 million, constitute a major milestone in the Sultanate of Oman’s drive to cut down the carbon footprint and limit demand for natural gas.
Ahmed Salim Al Abri, Acting CEO of Nama Power and Water Procurement Company, said that the production capacity of “Manah 1 and Manah 2” solar energy projects touches 1,000 megawatts, mainly through the use of solar photovoltaic technology.
The projects cover a total area of 14.5 million square meters and comprise more than two million square meters. The total length of their cables extends more than 3,000 km. The projects will supply power to more than 120,000 residential units.
Commercial operation of “Manah 1” project is expected to commence during the first quarter of 2025, while “Manah 2” project is expected to begin commercial operation in the second quarter of the same year.
Related
-
World Bank restarts ambitious Inga 3 hydro scheme in DRC
10 June 2025
-
Kenya and Ethiopia agree on multi-million cross-border infrastructure projects
9 June 2025
-
UK: TotalEnergies acquires a pipeline of solar and battery projects
9 June 2025
-
750 MWh Chilean battery achieve environmental approval
9 June 2025
-
EIB to provide €400m loan for Stockholm metro expansion
6 June 2025
-
Ferrovial acquires a 5.06% stake in the 407 ETR
6 June 2025