No extension for Dubai sewer tunnel prequalificationYou might also like...
25 April 2024Dubai Municipality expects interested engineering, procurement and construction (EPC) companies to submit their statements of qualifications (SOQs) by the end of April for the contracts to develop the Dubai Strategic Sewerage Tunnels (DSST) project.
“No further extension has been granted,” a source close to the project tells MEED.
International, regional and local EPC contractors are keen to prequalify to bid for the contracts for the $22bn DSST scheme, which Dubai Municipality is implementing on a public-private partnership (PPP) basis.
In addition to its size, the project is gaining significant interest due to its unique procurement approach, whereby EPC contractors’ prequalification precedes developers’ prequalification.
Dubai Municipality is undertaking the prequalification process for EPC contractors ahead of prequalifying companies that can bid for the contracts to develop and operate various packages of the project.
According to industry sources, the floods resulting from last week’s storm that hit Dubai and other emirates have also made implementing the project more urgent.
The bidders for each of the PPP requests for proposals (RFPs) will be prequalified consortiums comprised of sponsors, EPC contractors and operation and management (O&M) contractors.
MEED previously reported that the overall project will require a capital expenditure of roughly AED30bn ($8bn), while the whole life cost over the full concession terms of the entire project is estimated to reach AED80bn.
The project aims to convert Dubai’s existing sewerage system from a pumped system to a gravity system by decommissioning the existing pump stations and providing “a sustainable, innovative, reliable service for future generations”.
Dubai currently has two major sewerage catchments. The first in Deira is Warsan, where the Warsan sewage treatment plant (STP) treats the flow.
The second catchment, called Jebel Ali, is in Bur Dubai, where the wastewater is treated at the Jebel Ali STP.
DSST-DLT packages
Under the current plan, the $22bn DSST project is broken down into six packages, which will be tendered separately as PPP packages with concession periods lasting between 25 and 35 years.
The first package, J1, comprises Jebel Ali tunnels (North) and terminal pump stations (TPS). The tunnels will extend approximately 42 kilometres, and the links will extend 10km.
The second package, J2, covers the southern section of the Jebel Ali tunnels, which will extend 16km and have a link stretching 46km.
W for Warsan, the third package, comprises 16km of tunnels, TPS and 46km of links.
J3, the fourth package, comprises 129km of links. Once completed, Dubai Municipality will operate them, unlike the first three packages, which are envisaged to be operated and maintained by the winning PPP contractors.
J1, J2 and W will be procured under a design-build-finance-operate-maintain model with a concession period of 25-35 years.
J3 will be procured under a design-build-finance model with a concession period of 25-35 years.
J1, J2, W and J3 will comprise the deep sewerage tunnels, links and TPS (DLT) components of the overall project.
MEED understands the project’s remaining two packages, the expansion and upgrade of the Jebel Ali and Warsan STPs, will be procured in a process separate from the four DSST-DLT components.
The RFPs for the four DSST-DLT packages will likely be issued sequentially, staggered around six to 12 months apart.
Dubai Municipality has appointed Abu Dhabi-headquartered Tribe Infrastructure Group as lead and financial adviser, UK-based Ashurst as legal adviser and the US’ Parsons as technical adviser for the DSST project.
Related
-
North Macedonia kicks off 30 MW solar tender
29 November 2024
-
Serbia opens second renewables auction, tenders 124.8 MW of solar
29 November 2024
-
Serbia issues call to wind, solar power auctions with much lower ceiling prices
28 November 2024
-
Acciona signs Qatar 110MIGD desalination contract
28 November 2024
-
Samsung C&T to build $3.7bn power and water plant in Qatar
28 November 2024
-
Aecom, Jacobs hired for $7bn upgrade of Vancouver’s water system
28 November 2024