Zambia copper smelter scales back capacity amid hydropower shortage
13 March 2024The Chambishi Copper Smelter in Zambia, owned by China Nonferrous Metal Mining Corp (CNMC), has cut one-fifth of its production as it grapples with the fallout from power shortages across the country.
Zambia generates most of its electricity from hydropower, but output has taken a hit in recent months as ongoing droughts – the worst the country has seen in at least two decades – force water levels down.
The country’s state-owned power utility, Zesco, has also carried out several major maintenance projects on electrical infrastructure over the past six months. In November, it announced planned power outages as it worked to expand the transmission and distribution network in Zambia’s capital, Lusaka.
Zesco said last week that it would start rationing electrical supply from 11 March, but sources told Reuters that the Chambishi plant had already started reducing capacity as early as last week.
CNMC is reportedly considering installing diesel generators at the facility to ensure power security during times of electrical shortage, the sources added.
The plant produces approximately 250,000 tonnes of copper annually and is one of the biggest processing facilities in the country. Zambia currently stands as Africa’s second-largest copper producer, and last year it was the world’s eighth-biggest producer.
Related
-
CEEC JTC 118 MW solar project in Singapore connected to grid
10 January 2025
-
Skanska invests CZK 956M, about SEK 440M, in a new phase of a residential project in Prague, Czech Republic
10 January 2025
-
Renalfa IPP buys 258 MW solar project in Romania, plans to install 1 GWh BESS
10 January 2025
-
Norway plans SMR plant to power future data centres
9 January 2025
-
Croatia plans solar tenders in 2025
9 January 2025
-
Romania finances 1.5 GW solar panel factory
9 January 2025