Zambia copper smelter scales back capacity amid hydropower shortage
13 March 2024The Chambishi Copper Smelter in Zambia, owned by China Nonferrous Metal Mining Corp (CNMC), has cut one-fifth of its production as it grapples with the fallout from power shortages across the country.
Zambia generates most of its electricity from hydropower, but output has taken a hit in recent months as ongoing droughts – the worst the country has seen in at least two decades – force water levels down.
The country’s state-owned power utility, Zesco, has also carried out several major maintenance projects on electrical infrastructure over the past six months. In November, it announced planned power outages as it worked to expand the transmission and distribution network in Zambia’s capital, Lusaka.
Zesco said last week that it would start rationing electrical supply from 11 March, but sources told Reuters that the Chambishi plant had already started reducing capacity as early as last week.
CNMC is reportedly considering installing diesel generators at the facility to ensure power security during times of electrical shortage, the sources added.
The plant produces approximately 250,000 tonnes of copper annually and is one of the biggest processing facilities in the country. Zambia currently stands as Africa’s second-largest copper producer, and last year it was the world’s eighth-biggest producer.
Related
-
Masdar acquires 70% stake in Terna Energy
30 November 2024
-
Grew, Jakson, Jupiter Renewables, Saatvik to set up solar factories in India
30 November 2024
-
Skanska invests about SEK 530M in residential project in Täby north of Stockholm, Sweden
29 November 2024
-
ENERCON to install 2.5GW onshore wind capacity in Turkey
29 November 2024
-
Saudi Arabia secures metals investment deals worth $9.3bn
28 November 2024
-
India approves $1.05bn rail network expansion to boost connectivity
28 November 2024