Romania: 400 kV Portile de Fier-Resita transmission line completed
5 March 2024
Electricity transmission system operator Transelectrica completed the construction of the 400 kV overhead transmission line Portile de Fier-Resita. The total value of the project was 30 million euros. The works were executed by Electromontaj and Romelectro.
400 kV overhead transmission line Portile de Fier-Resita is the most complex, from a technical point of view, and difficult project carried out in Romania in the last 30 years, with its route crossing mostly mountainous areas, with rugged and difficult terrain.
The transmission line will be put into operation with the completion of the construction works of the 400 kV Resita substation, estimated for the second half of this year. At the same time, the new 400 kV Resita substation will enable the commissioning of the 400 kV Resita—Pancevo transmission line.
The new 400 kV overhead transmission line Portile de Fier-Resita has a length of 117 kilometers and consists of two sections: a new construction (Portile de Fier-Anina) and the modernization of an existing line (Anina–Resita).
Related
-
Scatec starts construction of the 900 MW Shadwan wind farm
13 October 2026
-
X-ELIO Inaugurates Its Largest Spanish Solar Plant in Lorca at 368 MW
13 October 2026
-
Bungaban Wind Farm (1.4GW) Secures Federal Environmental Approval in Australia
13 October 2026
-
Brime gas project, Norway
13 October 2026
-
US agency to do more equity investing in Africa, official says
10 October 2026
-
GEN İlaç (Türkiye) Inaugurates Pharmaceutical Plant in Azerbaijan
9 October 2026


京公网安备
11010802030424号
京ICP备19046776号-2