Greece: Alexandroupoli FSRU to deliver 45,000 MWh of natural gas per day
11 January 2024
The Alexandroupoli FSRU is expected to supply 45,000 MWh of natural gas to the Greek network daily. The facility, set for launch by March 10, will initially offer an annual capacity of 1.5 bcm, or 27 percent of its annual capacity, to the national system. A further 4 cm quantity will be supplied to the Bulgarian network via the IGB grid interconnection, and, by extension, Romania, North Macedonia, Serbia, and in any markets where traders that have signed contracts with Gastrade, the project’s consortium, have customers.
An initial LNG load, to be used for testing, is scheduled to reach the Alexandroupoli LNG on January 20. It will not stem from Russia as the project is designed to contribute to ending southeast Europe’s reliance on Russian gas.
The testing stage will entail filling a 28-kilometre gas pipeline, running mostly underwater, that connects the terminal with the Greek gas system, to check all systems and correct any minor issues so that the FSRU can be ready to operate commercially after six to seven weeks, or early March.
The FSRU, comprised of a floating storage unit with a capacity of 153,500 m3 and three gasification units, offering a daily gasification capacity of approximately 22.5 million m3, is a project of national significance that reinforces Greece’s role as an energy gateway to the markets of the wider region.
Related
-
China’s Panhua Group nears completion of Sarangani steel project‘s first phase
26 May 2026
-
Danantara Investment Management Announces the Results of the DPT BUPP PSEL Selection for Batch2
26 May 2026
-
Egypt prepares to tender five water treatment plants
26 May 2026
-
World Bank provides $2bn for Turkey railway corridor
25 May 2026
-
King Salman airport selects three contractors for apron ECI
24 May 2026
-
Japanese firm now fifth biggest US housebuilder after $4bn acquisition
22 May 2026


京公网安备
11010802030424号
京ICP备19046776号-2