Agreements reached on trans-Guinean infrastructure in milestone for Simandou iron ore project
17 August 2023Rio Tinto and the Simfer1 joint venture (Simfer) reached an important milestone today by concluding key agreements with the Republic of Guinea and Winning Consortium Simandou2 (WCS) on the trans-Guinean infrastructure for the world class Simandou iron ore project.
The Co-Development Convention with the Republic of Guinea and associated agreements adjusting Simfer and WCS’s existing mine conventions create the legal framework for the co-development of more than 600 kilometres of new multi-use rail together with port facilities, that will be used to export iron ore from the Simandou mining concessions in the southeast of the country.
Rio Tinto Executive Committee lead for Guinea and Copper Chief Executive Bold Baatar said “With these agreements we have reached an important milestone towards full sanction of the Simandou project, bringing together the complementary strengths and expertise of Rio Tinto and our partners, the Government of Guinea and Winning Consortium Simandou, for the infrastructure that will unlock this world class resource. Simandou, the world’s largest known undeveloped supply of high-grade, low-impurity iron ore, will strengthen Rio Tinto’s portfolio by complementing our existing Pilbara and Iron Ore Company of Canada products.”
The infrastructure capacity and associated cost will be shared equally between Simfer, which is developing blocks 3 and 4 of the Simandou project, and WCS, which is developing blocks 1 and 2. China Baowu Steel Group has also previously entered into a term sheet agreement with WCS that may see it partner in the WCS scope for blocks 1 and 2 of the Simandou mining concession and the infrastructure joint venture.
The Co-Development Convention requires ratification by the Guinean State. It is also subject to a number of conditions, including the Guinean State’s approval of the final feasibility study for the project. Negotiations continue between the partners to finalise the investment agreements and related shareholders’ agreements which underpin the co-development. A further announcement will be made when appropriate concerning these agreements.
Critical path works continue to be progressed by the partners to ensure progress is maximised during the 2023-24 dry season.
Related
-
Philippine distribution utility streamlines net-metering permits
30 November 2024
-
Eskom tenders 72 MW of solar at coal power plant
30 November 2024
-
Dat Bike gains momentum with $4 million boost
30 November 2024
-
Australia launches 6 GW wind, solar tender
30 November 2024
-
Kone wins Saudi Airport deal
30 November 2024
-
Masdar acquires 70% stake in Terna Energy
30 November 2024