India’s NTPC launches tender for 2 GW of pumped storage
14 July 2023NTPC Renewable Energy has started accepting bids to develop up to 2 GW of pumped hydro energy storage projects anywhere in India.
The pumped storage projects must be commissioned within five years from when they are awarded. The commissioning period includes 1.5 to two years for detailed project report preparation, land acquisition, studies, detailed engineering, and three to 3.5 years of construction period.
“Early completion of milestones would be acceptable and already built-up pumped storage projects would also be acceptable,” said NTPC Renewable Energy in the tender document.
Each developer must bid for a minimum of 200 MW (at a single location), rising in increments of 10 MW up to 2 GW (in single or multiple locations with a minimum of 200 MW at each location). The minimum storage cycle is six hours in all cases.
Related
-
EAC Hands Over Site For Kenya/Uganda Road Project
2 May 2024
-
Chicago Bears announces plans to build $4.2bn stadium
2 May 2024
-
Nigeria’s Ogun State Advances With Transport Projects
2 May 2024
-
Saudi Arabia foregoes April nuclear bid deadline
2 May 2024
-
Ugandan Parliament Approves Loan Request For Road
2 May 2024
-
Thai PM proposes world’s tallest building in Bangkok
1 May 2024