Indian government grants commissioning extension for solar projects on case-by-case basis
4 May 2023
India's Ministry of New & Renewable Energy (MNRE) has said solar or wind-solar hybrid projects for which bids were finalized before the announcement of the basic customs duty (BCD) on modules on March 9, 2021, would be granted commissioning extensions only on a case-by-case basis.
The renewable energy implementing agencies, including Solar Energy Corp. of India (SECI), NTPC and NHPC would examine developers’ requests for an extension on a case-by-case basis and grant extensions only if the developer has taken all possible measures to implement the project, such as land acquisition and orders for modules and balance-of-system supply, but couldn’t complete it for reasons beyond his control.
If the developer is yet to take steps to implement the project and is merely sitting on the award, such projects will not be granted an extension and will face cancellation.
Earlier, the MNRE had announced that solar and solar-wind hybrid projects for which bids were finalized before March 9, 2021, may be given time for completion up to March 31, 2024.
In its latest order, the MNRE has clarified that the completion extension for these projects is “not a general blanket extension”.
Related
-
Philippines proposes transmission grid reforms, updates to net-metering
15 July 2026
-
Investors, contractors warn EU that Chinese inverters ban jeopardizes energy transition in CEE
14 July 2026
-
Oman outlines grid plan for four 1GW solar IPPs
11 July 2026
-
Chile releases bidding terms for first energy auction including storage
16 June 2026
-
Serbia rolls out decrees on decarbonization incentives, tax credits
12 June 2026
-
Iraq risks defaulting on payments for $10bn oil project
21 May 2026


京公网安备
11010802030424号
京ICP备19046776号-2