Mandhoo Harbor dredging nears end
5 October 2022Maldives Transport and Contracting Company (MTCC) has just released the latest update on its Adh. Mandhoo Harbor Development Project
According to MTCC, the first shipment of precast concrete blocks required for quay wall construction for the project has been delivered to project site.
The dredging work on the new harbor basin is progressing well, with 94% completion so far.
Scope of works for the scheme includes:
- dredging and excavation operations of 65,854cbm;
- construction of a 236m quay wall;
- 319m breakwater;
- 71m revetment;
- 50m groynes.
Additionally, the installation of harbor streetlights, navigational aids and construction of 1180sqm of paved area will also be undertaken.
The value of the project is MVR 34.1 million ($2,2 million).
Related
-
WABAG awarded O&M contract for sewage treatment plant in Bahrain
26 August 2025
-
Japan’s Taisei offers $878m to buy rival Toyo Construction
22 August 2025
-
Saudi-Chinese joint venture to set up manufacturing facility in Kingdom
22 August 2025
-
Foster + Partners designs “green oasis” for Seoul
21 August 2025
-
Saudi Arabia's Neom seeks firms for Oxagon highway upgrade
21 August 2025
-
Egypt, China’s Ankura discuss localizing high-voltage cable industry
20 August 2025