Mandhoo Harbor dredging nears end
5 October 2022Maldives Transport and Contracting Company (MTCC) has just released the latest update on its Adh. Mandhoo Harbor Development Project
According to MTCC, the first shipment of precast concrete blocks required for quay wall construction for the project has been delivered to project site.
The dredging work on the new harbor basin is progressing well, with 94% completion so far.
Scope of works for the scheme includes:
- dredging and excavation operations of 65,854cbm;
- construction of a 236m quay wall;
- 319m breakwater;
- 71m revetment;
- 50m groynes.
Additionally, the installation of harbor streetlights, navigational aids and construction of 1180sqm of paved area will also be undertaken.
The value of the project is MVR 34.1 million ($2,2 million).
Related
-
Sinopec Guangzhou Engineering awarded with FEED contract for Yanbu green hydrogen project
3 August 2025
-
RWE secures environmental nod for 1,277 MWh solar-storage project in Chile
3 August 2025
-
Afreximbank backs 1 GW floating solar project in Zimbabwe
3 August 2025
-
OpenAI, Nscale and Aker to build massive ‘Stargate’ datacentre in Norway
3 August 2025
-
Aecom to deliver PMC, advisory services for Riyadh Integrated
2 August 2025
-
Portugal to hold energy storage auction before January 2026
1 August 2025