India’s Ireda launches tender for 2 MW canal-top solar project
20 September 2022
Jharkhand Renewable Energy Development Agency (JREDA) has started accepting bids to set up a 2 MW grid-connected canal-top solar project in the Ranchi district. The plant is to be built at the Sikdiri Canal near Sikidiri village.
The canal originates from the Getalsud Dam on the Subarnarekha river in the Angara Tehsil. It has a top width of around 21.77 meters and a depth of 4.27 meters. The length of stretch suitable for installation is 1.6 km.
The selected contractor’s scope includes design, engineering, procurement and supply, construction, commissioning, and power evacuation up to a 33 kV solar plant substation. It will be responsible for the comprehensive operation and maintenance of the plant for 10 years.
The contractor must employ solar PV modules of crystalline-silicon technology only. “The PV modules must be of minimum 72-cell configuration with a rated power of ≥300 Wp. The solar PV module shall have a maximum tolerance of +3%. No negative tolerance in the rated capacity of solar PV module is allowed,” states the tender document.
Related
-
On behalf of His Majesty King Abdullah II, His Royal Highness Prince Faisal bin Al Hussein lays the Foundation Stone for the National Water Conveyance Project, with Arab Contractors’ Participation
19 November 2026
-
Sabey Data Centers signs 10-year Texas solar agreement covering 43.5 MW
19 November 2026
-
$900bn Anthropic Data Centre Construction Bet Shapes AI Infrastructure Expansion
19 November 2026
-
$785M Los Alamos Computing Facility advances towards construction approval in University of Michigan
19 November 2026
-
Intermountain Health Breaks Ground on New 521,000-Square-Foot LDS Hospital in Salt Lake City
19 November 2026
-
Northern Vietnam's Hai Phong leases 103.6 hectares for Singapore-backed $945 mln port project
18 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2