Nags Head beachfill project starting soon
30 June 2022
Great Lakes Dredge & Dock Co. (GLDD) is almost ready to begin the 2022 beach nourishment project in the Town of Nags Head, North Carolina.
According to the latest update, the beach construction is now expected to take place from July 13 through early September 2022.
“Equipment mobilization is underway and de-mobilization is expected to take place in September,” the town said. “Remember, it is likely the schedule will change over the course of the project.”
The project, taking place over the next two months, includes dredging of approx. 975,000 cubic yards of beach-quality sand and placing it along a 4.5-mile section of oceanfront shoreline.
The work will start from 8031 South Old Oregon Inlet Road (Comfort Inn South) near Mile Post 16 south to Nags Head’s corporate limits abutting Cape Hatteras National Seashore near Mile Post 21.
Related
-
Iberdrola plans 1.32 GW pumped-hydro storage project in Portugal
28 July 2025
-
LG, Yahua Group to invest MAD 5.5 Billion in lithium refining plant in Morocco
28 July 2025
-
Jinko ESS and Solar commission 3.8 MWh energy storage system in Hungary
28 July 2025
-
Trina Storage strengthens APAC footprint with Japan-based deployment
28 July 2025
-
EDF shifts nuclear strategy to focus on domestic projects
27 July 2025
-
Poland seeks delivery partner for new international airport
27 July 2025