Nags Head beachfill project starting soon
30 June 2022
Great Lakes Dredge & Dock Co. (GLDD) is almost ready to begin the 2022 beach nourishment project in the Town of Nags Head, North Carolina.
According to the latest update, the beach construction is now expected to take place from July 13 through early September 2022.
“Equipment mobilization is underway and de-mobilization is expected to take place in September,” the town said. “Remember, it is likely the schedule will change over the course of the project.”
The project, taking place over the next two months, includes dredging of approx. 975,000 cubic yards of beach-quality sand and placing it along a 4.5-mile section of oceanfront shoreline.
The work will start from 8031 South Old Oregon Inlet Road (Comfort Inn South) near Mile Post 16 south to Nags Head’s corporate limits abutting Cape Hatteras National Seashore near Mile Post 21.
Related
-
Masdar and Engie achieve financial close for 1.5gw Khazna solar project in Abu Dhabi
22 January 2026
-
Dubai tenders Al-Maktoum airport metro link
21 January 2026
-
ACCIONA awarded road link project in southern São Paulo
21 January 2026
-
PIF signs agreement to develop Yanbu aluminium complex
17 January 2026
-
Montenegro’s power utility EPCG, Masdar sign cooperation agreement
16 January 2026
-
Xinyi Glass signed glass production project with Saudi’s MODON
15 January 2026


京公网安备
11010802030424号
京ICP备19046776号-2