Mexico conditionally approves 621 MW solar project in Veracruz

27 November 2026
Mexico conditionally approves 621 MW solar project in Veracruz

Mexico’s General Directorate of Environmental and Risk Impact (DGIRA), part of the Ministry of Environment and Natural Resources (Semarnat), has granted conditional environmental approval for the 621.17 MWp Cerro Colorado solar plant.

Developer Desarrollos y Soluciones Energéticas Eirene plans to build the project in the municipalities of Sayula de Alemán and Texistepec, in the state of Veracruz.

The project comprises 941,166 solar modules, each with a capacity of 660 W, and 1,803 Huawei SUN2000-330KTL-H1 inverters, each rated at 330 kW. The electrical infrastructure will include a 34.5 kV medium-voltage network and three 34.5/230 kV step-up substations.

The plant will cover a total area of 1,062.62 hectares across three sections, designated North, Central and South. Permanent infrastructure will occupy 296.90 hectares, equivalent to 27.94% of the project area, while 763.89 hectares will remain free of infrastructure.

The design also includes 19.86 km of new internal roads and the use of a further 13.67 km of existing roads. The environmental documentation also refers to battery energy storage systems (BESS), but does not specify their capacity.