Two companies are engaging with the tender process for the first phase of the project to develop an alternative feed system for the Al-Zour refinery’s hydrogen production units (HPUs), according to industry sources.
The two companies that are competing for the contract are:
Larsen & Toubro (L&T), India Tecnicas Reunidas (TR), Spain
Representatives from both companies attended a pre-tender meeting to discuss the project, which saw its bid deadline extended earlier this month.
The contract was re-tendered by state-owned Kuwait Integrated Petroleum Industries Company (Kipic) on 1 February.
In the latest rescheduling of the bid deadline, Kipic announced on 10 November that it was moving the submission date from 15 December 2026 to 19 January 2027.
The first phase of the project will enable the HPUs to use natural gas from the liquefied natural gas import terminal as an alternative to naphtha.
The contract is estimated to be worth $150m-$200m.
Kipic has been attempting to make progress with the project since at least 2023, when it first issued the tender. It set an initial bid submission deadline of 20 June 2023, which was then pushed back several times.
The original tender covered engineering, procurement and construction, along with pre-commissioning, start-up and quality testing.
The main element was the construction of Unit 38, a compression facility, including piping tie-ins and connections to process and utility headers in the existing interconnecting pipe racks.
The scope also included modifications and associated tie-ins for Unit 33, the existing HPU, and construction of Unit 60, a steam generation unit. It also covered the construction of two new boilers, modifications to extend the existing steam generation unit with all associated tie-ins, and associated facilities.
Kipic had initially contacted the following contractors, among others, to solicit their interest in the planned project:
Hyundai Engineering & Construction (South Korea) Larsen & Toubro Energy Hydrocarbon (India) Petrofac (UK) Samsung Engineering (South Korea) SK Engineering & Contracting (South Korea)
On 12 March 2024, MEED reported that a study was needed to determine how the refinery would process heavy oil and the exact specifications for several different units.
Ultimately, none of the contractors that were initially invited by Kipic to express interest in the project submitted bids, with only the following contractors submitting proposals in September 2024:
China Tianchen Engineering (China) Gulf Spic General Trading & Contracting (Kuwait) Heisco (Kuwait) Jereh Oil & Gas Engineering Corporation (China) Sinopec Luoyang Engineering (China)
All five of the technical bids received were deemed ineligible. Sinopec Luoyang Engineering’s bid was excluded for non-compliance with tender instructions, while the other four bids were rejected because Kipic determined that “none of the bidding companies met the technical qualifications required”.
The issuance of the latest tender for the project came nearly one and a half years after the first tendering round was shelved, during which time Kipic is understood to have been holding internal meetings about re-tendering the project, as well as working with relevant committees to secure the approvals required to initiate the new tendering process.
Related
-
Argentina LNG Project Targets 2031 Exports Following US$50.75 Billion RIGI Approval
24 November 2026
-
Three contractors compete for Kuwait LNG import project
24 November 2026
-
Contractors submit final offers for Oxagon infrastructure
24 November 2026
-
TechnipFMC Awarded Subsea Contracts for ExxonMobil Guyana’s Longtail Project
20 November 2026
-
Contractors submit technical bids for Bab Gas Cap project
20 November 2026
-
Equinor and Shell partner on the Bay du Nord project
17 November 2026


京公网安备
11010802030424号
京ICP备19046776号-2