Lower Arun Hydro Project: 669 MW, $650M Build Begins

25 November 2026

The Lower Arun hydro project has formally entered construction. On November 23, Indian Prime Minister Narendra Modi and Nepal’s Prime Minister Balendra Shah jointly laid the foundation stone for the 669 MW plant. They took part in a virtual ceremony from New Delhi, where Shah was on a two-day state visit.

What the Lower Arun hydro project involves

SJVN Lower Arun Power Development Company, a wholly owned subsidiary of India’s SJVN, is building the plant. It will have four generating units of 167.25 MW each. The estimated cost is ₹5,792.36 crore, which is about US$650 million, according to reports. Nepali media put the cost at NPR 92.67 billion. The project should generate about 2,901 million units of electricity a year, at a tentative tariff of ₹4.99 a unit. Commissioning is targeted for the 2030-31 financial year, and Nepal’s government says construction should finish within five years.

Who is building it?

Nepal awarded the project to SJVN through international competitive bidding on January 29, 2021. The two sides signed a project development agreement on June 1, 2023, under a build-own-operate-transfer model.

Contracts are already moving. DRA Infracon secured two civil engineering contracts worth about US$310 million combined, including more than 17 km of headrace tunnelling, according to a tunnelling trade report. In April, Patel Engineering emerged as the lowest bidder for Package 2, worth ₹1,593 crore, with a 54-month schedule.

The Lower Arun plant will work in tandem with SJVN’s 900 MW Arun-3 project, which lies upstream on the same river, about 35 km away. Water discharged from Arun-3 will feed Lower Arun, so the two plants share the same flow. In addition, the installed capacity grew from 474.25 MW to 669 MW during planning.

Under the agreement, Nepal receives 21% of the electricity free of charge. Nepali reports also describe a capacity royalty of NPR 400 per kW and a 7.5% energy royalty for 15 years after commercial operation starts. Therefore, the project supports Nepal’s energy security while giving India a larger power supply from its neighbor.

The plant will sit on the Arun River in Sankhuwasabha and Bhojpur districts, eastern Nepal.

s51.jpeg

What happens next?

The next steps are headrace tunnel excavation, powerhouse works, and the remaining civil packages. Watch for the Package 2 contract signing and for progress on tunnelling.